Trump Interior freezes five offshore wind builds, invoking classified national security risks

Trump Interior freezes five offshore wind builds, invoking classified national security risks

A sector already bruised by policy whiplash is now facing a stop sign mid-construction on the East Coast.

Overview

Offshore wind developers woke up thinking they were building power plants. They went to sleep realizing they were now building “national security risks,” at least in the Trump administration’s telling. Interior ordered an immediate pause on five major offshore wind leases already under construction.

The stakes are brutal and immediate: vessels stop, contractors idle, lenders reprice risk, and states counting on new electrons get pushed back again. The deeper fight is about who gets to define “security” in America’s energy buildout—engineers with mitigation plans, or political appointees with a kill switch.

Key Indicators

5
Projects paused while under construction
Vineyard Wind 1, Revolution Wind, CVOW-Commercial, Sunrise Wind, Empire Wind 1.
810 MW
Empire Wind 1 nameplate capacity
Equinor says the project is designed to power about 500,000 homes.
60%+
Empire Wind 1 completion claimed by developer
Equinor said the project was already more than 60% complete when halted again.
$3.1B
Empire Wind book value (incl. terminal) cited by Equinor
Equinor disclosed billions already invested and debt already drawn into the project stack.

People Involved

Doug Burgum
Doug Burgum
U.S. Secretary of the Interior (Ordered the December 2025 construction-lease pause; driving a broader offshore wind rollback)
Anders Opedal
Anders Opedal
CEO, Equinor (Leading a flagship U.S. offshore wind developer now hit by a renewed federal stop order)
Letitia James
Letitia James
New York Attorney General (Leading figure in multi-state legal pushback to Trump wind restrictions)
Judge Patti B. Saris
Judge Patti B. Saris
U.S. District Judge (District of Massachusetts) (Issued a key ruling undercutting Trump’s earlier wind freeze)

Organizations Involved

U.S. Department of the Interior
U.S. Department of the Interior
Federal Agency
Status: Used lease authority to pause construction-stage offshore wind projects

Interior controls federal offshore leasing and just pulled the emergency brake on projects already being built.

Bureau of Ocean Energy Management
Bureau of Ocean Energy Management
Federal Agency
Status: Interior bureau administering offshore wind leases and enforcing pauses/stop-work orders

BOEM is the permitting and leasing engine for offshore wind—and the mechanism for stopping it.

U.S. Department of Defense
U.S. Department of Defense
Federal Agency
Status: Cited as the source of classified risk assessments and radar concerns

The Pentagon’s radar and surveillance concerns are now the administration’s strongest political weapon against offshore wind.

Equinor ASA
Equinor ASA
Energy Company
Status: Developer of Empire Wind 1, now halted again

Equinor’s Empire Wind has become the political-risk test case for U.S. offshore wind financing.

Ørsted
Ørsted
Energy Company
Status: Developer of Revolution Wind and Sunrise Wind, both paused

Ørsted’s U.S. buildout is being hit where it hurts most: construction certainty and investor confidence.

Dominion Energy
Dominion Energy
Utility
Status: Developer of Coastal Virginia Offshore Wind (CVOW) Commercial, now paused

Dominion’s Virginia flagship offshore wind build is now caught in a federal security-driven freeze.

Avangrid
Avangrid
Energy Company
Status: Co-developer of Vineyard Wind 1, now paused

Avangrid’s Vineyard Wind 1 is a flagship U.S. project now halted midstream.

New York State Energy Research and Development Authority (NYSERDA)
New York State Energy Research and Development Authority (NYSERDA)
State Energy Agency
Status: Counterparty and policy driver behind New York offshore wind procurement

NYSERDA is the state-level engine trying to turn offshore wind into contracted, financeable reality.

Timeline

  1. Equinor halts work on Empire Wind 1, discloses financing exposure

    Money Moves

    Equinor says it is complying, warns of major impacts, and details sunk costs and debt already drawn.

  2. Interior pauses five construction-stage offshore wind leases

    Rule Changes

    Interior orders an immediate pause on five major projects, citing classified national security assessments and radar risks.

  3. Federal judge strikes down earlier Trump wind freeze

    Legal

    A prior attempt to broadly halt wind development is ruled unlawful, forcing a tactical pivot.

  4. Court lets Interior reconsider SouthCoast Wind approval

    Legal

    A judge allows the administration to revisit a Biden-era project approval, signaling permitting vulnerability.

  5. Interior launches offshore wind rules overhaul

    Rule Changes

    Interior starts a regulatory review and says new offshore wind approvals are paused during it.

  6. Interior moves to end “special treatment” for wind

    Statement

    Burgum announces measures targeting offshore wind lease sales and broader wind restrictions on federal lands.

  7. Trump issues wind-energy directive

    Rule Changes

    Interior later cites a presidential memorandum as the basis for pausing approvals and rewriting offshore wind policy.

Scenarios

1

Mitigation Deal Reopens Construction, With New Defense Conditions

Discussed by: Interior statements; developer disclosures; energy-sector reporting from Reuters and AP

Interior frames the pause as time to assess “mitigation” with leaseholders and states—so the cleanest exit is a negotiated package: radar upgrades, operational curtailments, adjusted turbine layouts, new monitoring, or funding commitments. Construction resumes, but with a precedent that Defense-driven conditions can be imposed midstream, raising costs and permanently widening the “political risk” premium for U.S. offshore wind.

2

States and Developers Sue, Court Orders Restart

Discussed by: AP coverage referencing prior successful state litigation; broader court-driven pattern in 2025 wind fights

After the earlier Trump wind freeze was struck down, states have a roadmap: argue Interior is re-running the same ban under a new label, using secrecy to dodge normal process. If a judge finds the pause procedurally defective or pretextual, Interior could be ordered to lift it quickly. But litigation takes time, and every month in court is a month of compounding construction and financing damage.

3

Pause Drags On, Projects Slip Years, U.S. Offshore Wind Becomes Unfinanceable

Discussed by: Market reaction and financing concerns highlighted by Reuters; developer warnings about delay impacts

If Interior refuses to define clear mitigation requirements—or keeps moving the goalposts—developers face a slow-motion collapse: missed installation windows, contract penalties, vessel and supplier demobilization, and lenders forcing restructures. The result isn’t a single cancellation headline but a sector-wide repricing where capital simply refuses to fund new U.S. offshore wind until policy changes.

4

Congress Steps In: Statutory Guardrails on Mid-Construction Lease Pauses

Discussed by: Not yet a dominant public forecast; implied by escalating federal-state conflict and infrastructure stakes

If job losses and rate impacts become politically painful in coastal states, lawmakers could push for limits on executive-branch authority to pause already-approved projects without transparent standards, timelines, and due process. The trigger is less ideology than economic fallout—ports, unions, and utilities demanding predictability. This is harder than it sounds in a polarized Congress, but the pressure increases with each halted project.

Historical Context

Cape Wind (Nantucket Sound) collapse

2001–2017

What Happened

Cape Wind was America’s first big offshore wind attempt, and it became a masterclass in delay: years of lawsuits, political opposition, and financing setbacks. Once key power purchase contracts unraveled, the project’s economic foundation cracked and it ultimately relinquished its federal lease.

Outcome

Short term: The pioneering project died without being built, chilling early U.S. offshore wind momentum.

Long term: The industry shifted toward larger, state-backed procurements and clearer federal pathways—until today’s backlash.

Why It's Relevant

It shows how “not canceled, just delayed” can still kill offshore wind once financing confidence breaks.

Wind turbine radar interference becomes a permanent national-security talking point

2000s–present

What Happened

As wind expanded near sensitive radar, agencies documented how turbines can create reflections and “clutter,” reducing detection and tracking performance. Over time, the issue evolved from niche engineering into a recurring approval chokepoint, often solvable with technical and procedural mitigation—until it’s weaponized as a veto.

Outcome

Short term: Mitigation workarounds emerged across agencies and developers to reduce operational impact.

Long term: Radar concerns remain a ready-made justification for restricting wind in contested locations.

Why It's Relevant

This is the technical kernel Interior is using to justify a sweeping construction-stage pause.

Block Island Wind Farm proves offshore wind can be built in the U.S.

2015–2016

What Happened

The Block Island project became the first U.S. offshore wind farm to reach commercial operations, demonstrating that permitting, marine construction, and grid connection were possible. It didn’t solve scale, but it broke the psychological barrier: offshore wind wasn’t hypothetical anymore.

Outcome

Short term: A functioning project validated ports, vessels, and early supply chain learning.

Long term: It helped catalyze the larger East Coast pipeline now vulnerable to policy reversals.

Why It's Relevant

It highlights what’s being interrupted now: the transition from “pilot success” to national-scale buildout.