Notable Quotes

I need a federal financial backstop that would cover 90 percent of the cost overruns over a contracted price to build another reactor. We have not reached a point in the U.S. where these first-of-a-kind projects can be built with any assurance that they will be on time and on budget.

Stories

America's unbuilt reactors

Rule Changes

Advocate for federal financial backstops

On March 4, 2026, the Nuclear Regulatory Commission approved a construction permit for TerraPower's Natrium reactor at Kemmerer, Wyomingโ€”the first permit for a commercial non-light-water reactor in more than 40 years. TerraPower broke ground on April 23 with Bechtel as general contractor, making Kemmerer the first utility-scale advanced nuclear plant under active construction in the US.