Construction begins on new O'Hare concourse as terminal expansion advances

Construction begins on new O'Hare concourse as terminal expansion advances

Built World Chicago, IL local

$917 million Concourse E will add 24 gates by 2034 and clear space for a larger Global Terminal.

Overview

Updated 1 hour ago

Chicago broke ground on Nov. 17 on Concourse E at O'Hare International Airport, a $917 million addition that will add 24 gates by 2034. The first 14 gates are scheduled to open in 2030; the final 10 arrive with the new Global Terminal.

The concourse is part of ORDNext, the city's $8.7 billion terminal expansion program. City officials say it will raise O'Hare's gate capacity by 14%, with construction funded by airport bonds repaid through airline landing fees and rent.

Why it matters

O'Hare's gate count determines which flights Chicago can add, and this is the first piece of a larger terminal replacement.

Last Monday's email for Chicago, IL

Sent Nov 16. It carried:

Get next Monday's: one short email a week. Free. Unsubscribe in one click.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

$917 million
Total Concourse E cost
Combined budget for both construction phases.
$640 million
Initial construction phase
Covers the first 14 gates, scheduled for 2030.
24
New gates at full build-out
Concourse E's total gate count by 2034.
14
Gates in first phase
Scheduled to open in 2030.
10
Gates added in second phase
Scheduled with Global Terminal completion in 2034.
465,000 sq ft
Concourse E floor area
Total size of the multilevel concourse.
315,000 sq ft
Passenger space
Space for gates, retail, dining and lounges.
14%
Increase in O'Hare gate capacity
Expected when the terminal expansion is complete.
$8.7 billion
ORDNext program cost
Includes Concourse D, Concourse E and the Global Terminal.
2.2 million sq ft
Planned Global Terminal size
Would replace the 64-year-old Terminal 2.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

2025 2034

5 events Latest: Yesterday
Tap a bar to jump to that date
  1. Concourse E and Global Terminal scheduled for completion

    Upcoming Schedule

    Final 10 gates open with the new Global Terminal.

  2. First 14 Concourse E gates scheduled to open

    Upcoming Schedule

    Initial construction phase is expected to be completed.

  3. Global Terminal construction scheduled to begin

    Upcoming Schedule

    The 2.2 million-square-foot terminal would replace Terminal 2.

  4. Groundbreaking held for Concourse E

    Latest Construction

    City and airline officials start the $917 million, 24-gate project; first phase due 2030.

  5. Concourse D construction begins at O'Hare

    Construction

    The 19-gate concourse is scheduled to open in late 2028.

Scenarios

1

Concourse E first phase opens with 14 gates in 2030

Possible Resolves by Jan 1, 2031

Discussed by: City officials and airline executives say the first phase is scheduled for 2030.

Construction proceeds through the initial $640 million phase, and the Chicago Department of Aviation opens the first 14 gates to passengers by the end of 2030. This is the schedule city officials announced at groundbreaking.

2

Concourse E opens all 24 gates by 2034

Possible Resolves by Jan 1, 2035

Discussed by: City officials and the project schedule presented at groundbreaking.

The second phase adds 10 more gates alongside completion of the O'Hare Global Terminal. If both projects stay on their announced timelines, Concourse E reaches its full 24-gate build-out in 2034.

3

Global Terminal construction slips past 2029

Possible Resolves by Jan 1, 2030

Discussed by: City officials currently say construction will begin in 2029; large airport projects often face schedule risk.

The Global Terminal is the centerpiece of ORDNext and the reason Concourse E is being built first. If its 2029 construction start slips, the final 10 Concourse E gates and the Terminal 2 replacement would likely move later.

Historical Context

3 moments from history that rhyme with this story — and how they unfolded.

1962

O'Hare Terminal 2 opens (1962)

Terminal 2 opened as part of O'Hare's Jet Age buildout, with a hard-edged design that defined the airport for decades. It has served United and American passengers for 64 years.

Then

It became a central piece of O'Hare's domestic hub operation.

Now

Its age and design limits helped drive the current plan to replace it with the Global Terminal.

Why this matters now

Concourse E is the first new concourse capacity meant to prepare for that replacement.

2016-2022

LaGuardia Airport Terminal B rebuild (2016-2022)

New York rebuilt LaGuardia's Terminal B in phases while the airport stayed open, using a public-private partnership. The project replaced a cramped terminal without closing the airport.

Then

Passengers moved through construction zones for years.

Now

The phased rebuild became a reference point for airport projects that cannot shut down operations.

Why this matters now

O'Hare is using a similar phased approach with Concourse D, Concourse E and the later Global Terminal.

1995

Denver International Airport opens late (1995)

Denver's new airport opened after delays and a failed automated baggage system. The airport eventually became a major hub.

Then

The opening was pushed back and the baggage system became a cautionary tale.

Now

The episode became a warning about mega-project schedules and complex airport systems.

Why this matters now

O'Hare's 2030 and 2034 milestones depend on coordinating construction, airlines and terminal systems across multiple phases.