Regulatory Agency
Appears in 1 story · Last updated Nov 25, 2026
Overseeing trial operations; further power increases need its approval.
Unit 1 ended its second grid test at 5:05 p.m. on Nov. 24 after almost 30 hours, longer than planned. It fed about 320 megawatts to Bangladesh's national grid and delivered electricity worth about 70.6 million taka (Tk 7.06 crore), the operator said.