Unit 1 ended its second grid test at 5:05 p.m. on Nov. 24 after almost 30 hours, longer than planned. It fed about 320 megawatts to Bangladesh's national grid and delivered electricity worth about 70.6 million taka (Tk 7.06 crore), the operator said.
Engineers are checking operating readings, turbine-generator performance and equipment; Nuclear Power Plant Company Bangladesh Limited (NPCBL) says the findings will guide the next steps. The plant is not yet in commercial operation; further power increases need approval from the Bangladesh Atomic Energy Regulatory Authority before the government's early-2027 target for full 1,200-megawatt output. Under the Russian contract, commercial supply is planned after 10 months of trials, and the eighth of nine planned uranium shipments arrived on Nov. 24.
Bangladesh has fed nuclear power into its grid twice; Rooppur's two units are set to add 2,400 megawatts.
Who makes nuclear power
Bangladesh is only the fourth country in 30 years to start making nuclear power
Each step is a country's first reactor feeding its power grid. 32 countries and Taiwan did it by 1996; since then only Iran, the UAE, Belarus and Bangladesh.
Bangladesh 2026
19542026
37
countries ever, Taiwan included by 2026
2026 Bangladesh
2020 Belarus, UAE
2011 Iran
1996 Romania
1991 China
1989 Mexico
Bangladesh is only the fourth country in 30 years to start making nuclear power
15 events
Latest: Yesterday
Showing 8 of 15
JK to step
Tap a bar to jump to that date
Jump to
November 2026
Eighth Russian fuel shipment arrives
LatestFuel Delivery
Three trucks carried the consignment into the Ishwardi site under army and law-enforcement security. The project has now received eight of nine planned Russian shipments, including one for Unit 1 refuelling and seven for Unit 2.
Second grid test ends after nearly 30 hours
Trial Operation
Unit 1 was disconnected from the national grid after nearly 30 hours supplying about 320 megawatts. The test delivered electricity worth about Tk 7.06 crore; engineers then began checking operating parameters, turbine-generator performance and related equipment.
Unit 1 begins second trial grid supply
Trial Operation
Unit 1 resumed supplying 300-350 MW to the national grid for tests expected to last 10 to 24 hours. Project Director Dr Md Kabir Hossain said engineers would check the generation system and its operation with the grid.
Unit 1 connects to national grid
Milestone
Rooppur Unit 1 supplied its first electricity to the national grid at 3:16pm, reaching 350 MW before operators reduced output to 300 MW for stability tests.
First trial grid supply ends after 8 hours 34 minutes
Trial Operation
Unit 1 generated a maximum of 375 MW before the grid disconnection at 11:50pm. It had supplied power for 8 hours 34 minutes, after being reduced to 300 MW for grid stability and later raised gradually.
October 2026
Unit 1 begins power generation process
Milestone
Operators began raising reactor pressure and temperature, starting the C-stage tests that lead to electricity generation.
BAERA approves C-stage power start-up
Regulatory
The regulator allowed Unit 1 to enter the final stage of raising reactor power, clearing the way for turbine-generator tests.
Rosatom completes automated process control systems installation
Milestone
Rosatom announced completion of installation of automated process control systems at both Rooppur units.
Unit 1 achieves first criticality
Milestone
Unit 1 begins a self-sustaining chain reaction at 3:34pm; BAERA starts an inspection of the reactor's readiness.
Minister meets Rosatom chief in Moscow
Diplomacy
Science minister Fakir Mahbub Anam meets Rosatom DG Alexey Likhachev; Rosatom targets late-November power generation.
Regulator approves fission start
Regulatory
BAERA grants B2 sub-stage authorization, permitting Unit 1 to begin its first controlled fission reaction.
First fuel consignment for Unit 2 arrives
Milestone
The first nuclear fuel for Rooppur Unit 2 arrived at the site, moving the second reactor closer to its own commissioning.
September 2026
Safety valve defects delay fission start
Setback
Defects found in safety valve tests push the planned September start of fission to a later date.
April 2026
Fuel loading begins at Unit 1
Milestone
Rosatom's engineering division begins loading nuclear fuel into Unit 1's reactor vessel.
2011
Bangladesh, Russia sign Rooppur deal
Agreement
Bangladesh and Russia sign an intergovernmental agreement for the 2,400 MW Rooppur plant, with Rosatom as constructor.
Scenarios
1
Rooppur Unit 1 feeds 300 MW into Bangladesh's grid by December
Likely
Resolves by End of 2026
Discussed by: Rosatom Director General Alexey Likhachev and NPCBL officials, who told reporters trial grid supply could start in late November or December.
This happened on Nov. 17, when Unit 1 supplied 300-350 megawatts for eight hours and 34 minutes. A second run on Nov. 23 delivered about 320 megawatts for nearly 30 hours before disconnection on Nov. 24.
2
Commissioning delays push Rooppur's grid connection into 2027
Possible
Resolves by Feb 1, 2027
Discussed by: Project officials quoted by The Business Standard, who note the timeline is not fixed and could stretch to 10 weeks from mid-October.
The first grid connection already happened on Nov. 17, so later slips would affect higher output or commercial operation, not the initial connection. The process had already slipped once when safety-valve defects pushed fission from September to October.
3
Rooppur Unit 1 reaches full commercial operation
Uncertain
Resolves by End of 2027
Discussed by: Rosatom, which expects trial operations to continue seven to eight months before commercial declaration.
After the trial period — which officials say could run seven to eight months — the reactor must demonstrate sustained performance at or near its 1,200 MW design capacity. Full commercial operation is the formal end of the commissioning arc, likely in the second half of 2027.
4
Rooppur Unit 1 reaches full commercial operation by February 2027
Possible
Resolves by Feb 28, 2027
Discussed by: Science and Technology Minister Fakir Mahbub Anam
The government aims to raise Unit 1 to its full 1,200 MW and declare commercial operation in February 2027. Trial runs and reliability tests continue through December and January, and BAERA must approve each stage.
5
Rooppur Unit 1 enters a 10-month trial period before commercial supply
Possible
Resolves by Sep 17, 2027
Discussed by: The Financial Express, citing the agreement with the Russian contractor
Project sources say trial runs are following International Atomic Energy Agency guidelines. The agreement with the Russian contractor plans commercial electricity supply from Unit 1 after 10 months of trial operation.
Historical Context
2 moments from history that rhyme with this story — and how they unfolded.
1 of 2
2020–2021
UAE Barakah Unit 1 (2020–2021)
The United Arab Emirates built the Arab world's first nuclear plant at Barakah with South Korean technology from KEPCO. Unit 1 loaded fuel in early 2020, reached criticality that year, and connected to the grid in April 2021 — roughly a year after fuel loading began.
Then
The UAE grid took on its first nuclear power, starting with a single unit before ramping the rest of the four-reactor plant.
Now
The UAE says Barakah can supply up to a quarter of its electricity, and the program became a template for first-time nuclear countries in the region.
Why this matters now
Barakah shows the typical path for a first-time nuclear country: a foreign-built reactor, staged regulatory approvals, and a gradual ramp from first criticality to grid supply.
2 of 2
September 2011
Iran Bushehr (2011)
Russia completed Iran's Bushehr plant after German contractor Siemens abandoned the project following the 1979 revolution. The VVER-1000 reactor was connected to the grid in September 2011, decades after construction began.
Then
Bushehr added roughly 1,000 megawatts gross to Iran's grid, its first nuclear generation.
Now
Iran remains the only Middle Eastern country operating a Russian-built reactor, and Bushehr became a fixture in nuclear diplomacy.
Why this matters now
Like Rooppur, Bushehr is a Russian-built VVER reactor at the center of a national power program — though Rooppur's commissioning has moved far faster since fuel loading began in April 2026.