Building 1.66 GW of battery storage in the first fast-track batch
PJM Interconnection accepted a fourth fast-track project on Nov. 10: a 500-megawatt battery storage facility proposed by Little Blue Solar in Beaver County, Pennsylvania. The approval brings the fast-track total to 2,615 megawatts, including Engie's 1.66 gigawatts of storage and LS Power's 455-megawatt gas uprate, all targeted for mid-2029.
Updated Nov 17