Commissioned the projects; sets national capacity targets
The Gombe transmission substation had 300MVA of upstream capacity, carried by two 150MVA transformers, and 150MVA downstream. Demand across Gombe and the neighbouring North-East states had outgrown that layout. On 19 November 2026, the Minister of Power commissioned a third 300MVA transformer there and a new 120MVA substation at Billiri.