Nigeria commissions Billiri substation and doubles Gombe transmission capacity

Built World

Two projects on one day lift upstream capacity at Gombe to 600MVA and add a 120MVA station serving Billiri and Numan

Overview

Updated 36 minutes ago

The Gombe transmission substation had 300MVA of upstream capacity, carried by two 150MVA transformers, and 150MVA downstream. Demand across Gombe and the neighbouring North-East states had outgrown that layout. On 19 November 2026, the Minister of Power commissioned a third 300MVA transformer there and a new 120MVA substation at Billiri.

Gombe's upstream capacity is now 600MVA, and downstream capacity rose to 220MVA after a 30MVA unit was replaced with a 100MVA one. Billiri adds 120MVA of its own, connected to the existing Gombe–Zabana–Yola line with six outgoing 33kV feeders. These are transformation gains, not generation. The extra capacity only translates into supply if power is produced upstream and Jos Electricity Distribution Company takes it downstream.

Why it matters

Gombe's transmission ceiling has doubled. Whether households get more electricity now depends on Jos DisCo's offtake, metering and bill collection.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

600 MVA
Gombe substation upstream capacity
Doubled from 300MVA with the addition of a 300MVA, 330/132kV transformer, about 480MW.
120 MVA
Billiri substation capacity
Two 60MVA transformers, roughly 96MW, built with World Bank funding.
220 MVA
Gombe substation downstream capacity
Up from 150MVA after a 30MVA transformer was replaced with a 100MVA unit, about 176MW.
70,000+
Additional households expected to gain supply
TCN's projection for Gombe and neighbouring parts of the North-East, including Yobe State.
~10,000 MW
Transmission capacity added nationwide in six months
The Minister of Power's figure, stated at the Gombe commissioning; the administration targets about 19,000MW.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

June 2021 November 2026

6 events Latest: Today
Tap a bar to jump to that date
  1. Project funding and contractors detailed in national coverage

    Today Announcement

    Reports identify the World Bank-funded Billiri build by Chris Ejik International and the ISIN-built Gombe transformers.

  2. Minister says grid added close to 10,000MW in six months

    Statement

    Tegbe sets a 19,000MW transmission target and says another 5,000MW should come within two to three months.

  3. Minister commissions Billiri substation and Gombe upgrade

    Commissioning

    Tegbe opens the 2x60MVA Billiri station, then a 300MVA and a 100MVA transformer at Gombe, doubling upstream capacity to 600MVA.

  4. Gombe substation upgrade completed

    Construction

    TCN finishes the work five years after award, ahead of formal commissioning.

  5. Electricity Act signed into law

    Legislation

    The law ends federal exclusivity over electricity supply and gives states authority over their own markets.

  6. TCN awards Gombe transformer contract

    Contract

    ISIN Electromechanical Industries Limited wins the job to add a 300MVA, 330/132kV transformer and upgrade the downstream side at Gombe.

Scenarios

1

Gombe households see more hours of supply as Jos DisCo lifts offtake

Likely Resolves by Q3 2027

Discussed by: TCN and the Ministry of Power, which framed both projects around Jos DisCo's ability to take more power

The transformers only matter if the distribution company draws more current through them. TCN's managing director used the commissioning to ask Jos DisCo to maximise available capacity. If the company does, households in Gombe and nearby Yobe communities see longer supply hours within a year.

2

New transformers sit half-used as distribution lags

Possible Resolves by Q3 2027

Discussed by: Business Times, which noted the projects expand installed transformation capacity rather than generation

Capacity on a substation is not the same as power delivered. If Jos DisCo's network, metering or collections cannot absorb the extra current, TCN ends up with transformers rated above what the franchise takes. The tell would be officials describing available capacity that nobody is buying.

3

Vandals strip a new transformer and supply falls back

Possible Resolves by Nov 30, 2027

Discussed by: Minister of Power Joseph Tegbe, who devoted part of his Billiri speech to the risk

Tegbe told residents the equipment was their asset and warned that vandalism could undermine the benefits. Substation theft of oil, cables and fittings is a recurring problem on Nigerian installations. One serious strike at Billiri or Gombe would cut capacity and hand the region back part of the constraint just removed.

4

Federal Government commissions the next 5,000MW of transmission capacity

Uncertain Resolves by Q1 2027

Discussed by: Minister of Power Joseph Tegbe, speaking in Gombe on 20 November 2026

Tegbe said projects due for completion within two to three months would add another 5,000MW to the national network, on the way to a 19,000MW target. Delivering that would confirm the Gombe commissioning was part of a working pipeline rather than a one-off. Slippage would suggest the targets are aspirational.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

November 2013

Nigeria's power sector privatisation (2013)

Nigeria sold its state power company's generation and distribution arms to private buyers, handing the grid's retail and production ends to investors. Transmission stayed in federal hands under the Transmission Company of Nigeria, on the argument that a single national grid needed a single operator.

Then

Private owners took over distribution companies, including the one serving Gombe, and inherited networks with weak metering and collection.

Now

Transmission investment stayed dependent on federal budgets and lenders. Substations like Billiri are built with World Bank money rather than private capital.

Why this matters now

The split explains why a 120MVA substation is commissioned by a federal minister and funded by a development bank, while the customers who benefit are billed by a private distribution company.

2023

Electricity Act 2023

President Bola Tinubu signed a law ending the federal government's exclusive control over electricity supply. States gained the power to license and regulate generation, transmission and distribution within their borders, and to set up their own markets.

Then

States began setting up electricity regulators and courting generators and mini-grid developers.

Now

The national grid remained the backbone, but state governments took on a direct role in whether new capacity reaches customers.

Why this matters now

Gombe's representative thanked Tinubu for the law at the commissioning. The state now has formal authority over the intrastate supply that has to absorb Billiri's 120MVA.