Boston spent years planning a signature transit upgrade: extending its center-running bus lanes on Columbus Avenue north to Ruggles Station. The city has now dropped that design and will build curbside bus lanes instead, with construction starting in 2027 and lasting up to 18 months.
Updated 6 days ago
Tracking MBTA shutdown data, supporting results
The Green Line's central tunnel reopened October 5 after nine days of signal work. Crews installed 40 of 72 planned miles of new cable and 85% of junction boxes. Another nine-day closure starts November 7, with more shutdowns set for late October and December.
Updated Oct 17