Denver auditor finds National Western Center lacks financial goals and accountability

Denver auditor finds National Western Center lacks financial goals and accountability

Built World Denver, CO local

Seven straight years of operating deficits at the redeveloped campus, with performance benchmarks not due until 2028

Overview

Updated 57 minutes ago

Residents of Globeville, Elyria and Swansea asked Denver's auditor to check how bond money for the National Western Center was being spent. The answer, published in November 2026, describes a campus with seven straight years of operating deficits, no measurable financial goals, and a neighborhood donation fund whose balance could not be verified.

In 2025 the center ran 81 events, up from 27 in 2023, on $3.9 million in operating revenue against $16.1 million in expenses. The National Western Center Authority accepted 27 of the auditor's 28 recommendations, but does not expect to publish performance benchmarks until June 2028.

Why it matters

Denver voters backed this campus with $778 million in bonds in 2015; the audit says the city still cannot show it is becoming self-sustaining.

Last Monday's email for Denver, CO

Sent Nov 23. It carried:

Get next Monday's: one short email a week. Free. Unsubscribe in one click.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

$3.9M
Operating revenue, 2025
Revenue reported by the National Western Center Authority for the 2025 fiscal year.
$16.1M
Operating expenses, 2025
Expenses ran about $12.2 million ahead of operating revenue.
7
Consecutive years of operating deficits
The audit counted deficits in every year from 2019 through 2025.
81
Events hosted in 2025
Up from 27 events in 2023, though attendance data was incomplete.
60
Events with attendance records, 2023-2025
Out of 149 events; most figures were rounded or supplied by organizers without documentation.
$778M
Bonds authorized by Denver voters in 2015
The package covered the National Western Center and the Colorado Convention Center.
27 of 28
Audit recommendations accepted
Implementation deadlines run into 2028.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

1906 November 2026

7 events Latest: Yesterday
Tap a bar to jump to that date
  1. Denverite reports audit found frayed neighborhood ties

    Latest Media

    Coverage centers on the broken relationship with Globeville, Elyria and Swansea and the unverifiable donation fund.

  2. Event count rises as revenue gap widens

    Financial

    81 events produced $3.9 million in operating revenue against $16.1 million in expenses.

  3. Operating deficits begin

    Financial

    The first of seven consecutive years in which expenses exceeded operating revenue.

  4. Voters authorize $778 million in bonds

    Policy

    The ballot measure covered National Western Center improvements and the Colorado Convention Center.

  5. Stock Show considers leaving Denver

    History

    City officials pursued a redevelopment plan to keep the show and turn the complex into a year-round destination.

  6. National Western Stock Show begins in Denver

    History

    The annual livestock show traces back to Denver's stockyard industry in the 1880s.

Scenarios

1

Authority publishes benchmarks and passes its first independent audit

Possible Resolves by Jul 31, 2028

Discussed by: Denver Auditor's Office and National Western Center Authority, both of which set the June 2028 target

The authority agreed to establish measurable performance goals and hire an independent auditor in 2027, with the first performance review following the Livestock Center's first full year of operations. If those deadlines hold, the center would have a documented standard to be judged against for the first time.

2

City records show how the $12.2 million gap was covered

Likely Resolves by Nov 30, 2027

Discussed by: Auditors and city budget watchers, who noted it was not immediately clear how the authority closed its 2025 shortfall

The audit found the authority reported $3.9 million in operating revenue against $16.1 million in expenses in 2025, but did not establish how the gap was filled or how much city money, if any, was involved. A future city budget document or financial report showing a specific transfer would settle the question.

3

Deficits persist after the benchmarks arrive

Possible Resolves by Q2 2028

Discussed by: Auditor Timothy O'Brien, who said current revenue levels do not show progress toward sustainability

If event growth does not close the gap, the authority would enter its benchmark year still spending more than it earns. That outcome would put the city in the position of either funding the shortfall or accepting a structural deficit at a campus built to be self-sustaining.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

2011

Stock Show relocation threat (2011)

The National Western Stock Show, held in Denver since 1906, considered leaving the city. City officials responded with a redevelopment plan meant to keep the show and turn the aging complex into a year-round destination for agricultural, educational and entertainment events.

Then

Denver committed to rebuilding the complex rather than losing the Stock Show.

Now

The plan grew into a campus with a 350,000-square-foot livestock center and a reported project cost of $1.5 billion.

Why this matters now

The center's current form exists because Denver chose to invest rather than lose an anchor event. The audit asks whether that choice is producing a venue that pays for itself.

2015

Denver's $778 million bond authorization (2015)

Denver voters approved a ballot measure authorizing $778 million in bonds for National Western Center improvements and the Colorado Convention Center. The vote is the legal basis for the public money now under review.

Then

Construction proceeded on a multi-year campus rebuild.

Now

The authority has reported operating deficits every year from 2019 through 2025, with no measurable performance targets in place.

Why this matters now

The audit measured the campus against the promise attached to that 2015 vote: public money for an institution that would eventually stand on its own.

Sources