Meta-backed solar plant breaks ground in rural Arkansas

Meta-backed solar plant breaks ground in rural Arkansas

Built World

EDP Renewables starts building a 250-megawatt project in Chicot County six months after signing a long-term power purchase agreement with Meta

Overview

Updated 6 hours ago

EDP Renewables North America began construction on Cypress Knee Solar, a 250-megawatt plant on roughly 2,200 acres of flat farmland near Lake Village in Chicot County, Arkansas. The company announced the groundbreaking on November 4, six months after signing a long-term power purchase agreement with Meta.

The plant is due to run by 2028 and accounts for nearly half of the 545 megawatts Meta has now contracted with EDP Renewables. For Chicot County, the return is tax revenue: about $25 million over 30 years through an industrial revenue bond, with the largest share going to the Lakeside School District.

Why it matters

Chicot County collects roughly $830,000 a year for 30 years from a solar farm whose electricity a tech company buys.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

250 MW
Plant capacity
Cypress Knee Solar's generating capacity, enough for more than 43,000 Arkansas homes at a 25% capacity factor.
$25M
Lifetime payments to Chicot County
Revenue paid over the project's 30-year life under an industrial revenue bond agreement.
545 MW
Total Meta-EDPR contracted capacity
Cypress Knee is the third deal between the two companies and nearly half of the total.
$400M+
Estimated capital investment
EDP Renewables' published estimate for building the project.
43,400
Arkansas homes matched
Equivalent household consumption, calculated at a 25% capacity factor.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

May 2026 November 2026

2 events Latest: Today
  1. Cypress Knee Solar breaks ground in Chicot County

    Today Construction

    EDP Renewables announced the start of construction on November 4; the plant is scheduled to run by 2028.

  2. Meta and EDP Renewables sign 250 MW power purchase agreement

    Contract

    The deal is the third between the two companies and brings their total contracted capacity to 545 megawatts.

Scenarios

1

Cypress Knee Solar enters commercial operation by the end of 2028

Likely Resolves by End of 2028

Discussed by: EDP Renewables project announcements and its published construction timeline

EDP Renewables has said the plant will be complete in 2028, and construction began on schedule six months after the contract was signed. If procurement and interconnection hold, the county's roughly $830,000 annual payment stream starts in 2029.

2

Construction slips past 2028 and payments start late

Possible Resolves by Q2 2029

Discussed by: No public forecaster; the risk is implied by the gap between the 2027 date in earlier project materials and the 2028 date in the November announcement

EDP's earlier fact sheet listed an estimated commercial operation date of 2027, and the November release says 2028. A further slip would delay the county's revenue and push the plant's output past the current contract window.

3

Meta and EDP Renewables sign a fourth power purchase agreement

Possible Resolves by End of 2027

Discussed by: Trade press covering the companies' expanding procurement relationship

Each of the three deals has been larger or comparable to the last, and Meta continues to contract generation for its data centers. A fourth agreement would extend the pattern into another state or another Arkansas project.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

2024

Brittlebush Solar Park, Arizona (2024)

EDP Renewables built a 200-megawatt solar plant in Pinal County, Arizona, with Meta contracted to buy the output to support its data center in Mesa. It was the first of the two companies' power purchase agreements.

Then

The plant gave Meta a template for contracting new generation rather than buying renewable energy credits.

Now

Two more deals followed, including Cypress Knee, bringing the pair's total to 545 megawatts.

Why this matters now

Cypress Knee repeats the Brittlebush structure: a developer builds, a tech company buys the output, and the host county collects property tax revenue.

August 2022

Inflation Reduction Act (August 2022)

The law set long-term federal tax credits for solar and wind generation, replacing a cycle of short-term extensions that had made project financing harder to plan.

Then

Developers gained a multi-year window to underwrite projects and sign long-term contracts.

Now

Utility-scale solar construction accelerated across the South, including states with little prior solar capacity.

Why this matters now

The credits underpin the economics that let EDP Renewables offer Meta a fixed long-term price for Arkansas generation.