9 Dock rebuild, Devonport (1999–2002)
The dock next to 10 was rebuilt to take the Vanguard-class ballistic missile submarines. The job ran about three years and finished roughly £283m over budget.
The dock returned to service in January 2002.
It became the cost and schedule benchmark against which later Devonport dock work is judged.
Same site, same class of nuclear-licensed civil engineering, same overrun risk. It is the reason analysts are sceptical of a one-year build at 10 Dock.