BMD wins contract to build Tonkin Highway interchange at North Ellenbrook

BMD wins contract to build Tonkin Highway interchange at North Ellenbrook

Built World

The A$100 million interchange is the access point for 12,500 planned homes in Perth's north-east

Overview

Updated 51 minutes ago

Main Roads Western Australia has chosen BMD Constructions to design and build a new interchange on Tonkin Highway, between Maralla Road and Warbrook Road north of Ellenbrook. The job is estimated at A$100 million and is the road access for a district plan calling for more than 12,500 homes.

Land release in North Ellenbrook depends on the interchange being built, so the housing waits on this contract. Construction is due to start in late 2026 and finish in late 2028, about a year later than the schedule Main Roads published in 2025.

Why it matters

Perth's next 36,000-resident suburb depends on one interchange; the contract sets when 12,500 homes can be released.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

A$100m
Estimated project cost
Funded by A$50 million federal, A$25 million state and A$25 million private investment.
12,500
Homes planned in North Ellenbrook
Across the east and west district structure plans over the next 20 years.
36,000
Future residents supported
Main Roads' projected population for the district plans.
8,000
Jobs projected in nearby Bullsbrook industrial land by 2040
About 270 hectares north of the development are proposed for industrial use.
Late 2028
Targeted completion
Construction is expected to begin in late 2026.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

Organizations Involved

Timeline

May 2022 November 2026

5 events Latest: Today
Tap a bar to jump to that date
  1. Award reported at an estimated A$100 million

    Today Contract

    Trade press reported the design and build deal, with construction targeted for late 2026.

  2. BMD publishes its project announcement

    Contract

    The contractor confirmed the award publicly, seven weeks after the state announcement.

  3. WA government awards the contract to BMD

    Contract

    BMD Constructions was selected to design and build the interchange, underpass and shared path realignment.

  4. Main Roads opens expressions of interest

    Procurement

    Tender EOIMRWA030824 was published, with responses due 27 August 2025.

  5. Governments commit funding for a new interchange

    Funding

    The 2022-23 state budget allocated A$50 million federal, A$25 million state and A$25 million private money.

Scenarios

1

Major construction starts in late 2026

Likely Resolves by Q1 2027

Discussed by: Main Roads Western Australia and the WA Government's contract award statement

BMD finishes detailed design and mobilisation, and site preparation may run before major work begins. Main Roads now says construction starts in late 2026, a few months later than the August-September 2026 start in its own 2025 schedule.

2

Interchange opens to traffic by late 2028

Possible Resolves by Q1 2029

Discussed by: Main Roads Western Australia and BMD Constructions

The single-point urban interchange, new underpass and realigned Principal Shared Path are finished and opened to traffic and pedestrians within the targeted window, keeping the North Ellenbrook land release on its current timetable.

3

A second-stage Warbrook Road overpass gets funded

Unlikely Resolves by Q2 2029

Discussed by: Main Roads Western Australia's 2025 sustainability report

The project case anticipates a future overpass north of the interchange and widening of Tonkin Highway by 2051. Main Roads says rezoning land between Warbrook Road and Chitty Road to urban needs further investigation before the overpass location is fixed. No funding has been announced for that stage.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

2022

North Ellenbrook interchange budget commitment (2022)

In the 2022-23 state budget, the McGowan Labor Government committed to building an interchange on Tonkin Highway north of Ellenbrook. The money came from three sources: A$50 million federal, A$25 million state and A$25 million from private investors.

Then

The project went to market three years later, with expressions of interest opening in July 2025.

Now

The estimated cost still sits at about A$100 million, the same total the three funding sources add up to.

Why this matters now

It shows the gap between an announced road project and a signed contract. Here it ran about four years.

2025

Main Roads' original delivery schedule (2025)

Main Roads' 2025 sustainability report set contract award for March 2026, construction start for August or September 2026, and completion for late 2027. The agency said procurement would run in parallel with project development and environmental approvals to hold that timeline.

Then

The contract was awarded in October 2026, seven months after the planned date.

Now

Completion is now targeted for late 2028, roughly a year later than the 2025 plan.

Why this matters now

Read the current late-2026 start and late-2028 finish as revised targets, not first estimates.

Sources