Pull to refresh
Logo
NSF stands by KBR for $8 billion Antarctic contract despite GAO ruling

NSF stands by KBR for $8 billion Antarctic contract despite GAO ruling

Money Moves

Agency says it resolved watchdog's concerns about how it evaluated the winning bidder

Yesterday: NSF says it resolved GAO concerns, backs KBR

Overview

Updated 1 hour ago

The National Science Foundation is keeping KBR as its contractor to run U.S. Antarctic research stations, saying it has resolved concerns raised by the government's contract watchdog. The $8 billion, 20-year award was challenged by rival bidder Battelle Memorial Institute.

The Government Accountability Office found in September that NSF improperly credited KBR with the experience of its affiliate company, Trinzic, when evaluating bids. Researchers also worry about KBR's plan to hire foreign workers at below-market wages, which they say could threaten national security.

Why it matters

An $8 billion, 20-year contract for U.S. Antarctic research support hangs on whether NSF's re-evaluation satisfies the GAO's concerns.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

$8 billion
Contract ceiling value
The maximum value of the 20-year Antarctic support contract awarded to KBR.
40%
KBR's bid below Battelle's
KBR bid $8.4 billion, about 40% less than Battelle's $13.8 billion bid.
3
U.S. research stations in Antarctica
The three year-round stations KBR would operate under the contract.
20 years
Contract duration
The period of performance for the Antarctic support contract.

Voices

Curated perspectives — historical figures and your fellow readers.

Ever wondered what historical figures would say about today's headlines?

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

May 2025 October 2026

5 events Latest: Yesterday
Tap a bar to jump to that date
  1. NSF says it resolved GAO concerns, backs KBR

    Latest Statement

    NSF says it 'fully complied' with GAO's recommendations and keeps KBR as the awardee, lifting the stay on the contract.

  2. NSF awards $8 billion Antarctic contract to KBR

    Award

    NSF awards a 20-year, $8 billion contract to KBR to run U.S. Antarctic research stations.

  3. NSF issues request for proposals for Antarctic support

    Procurement

    NSF issues RFP for science and engineering support services in Antarctica, including operating three research stations.

Scenarios

1

NSF Reaffirms KBR Award After Re-Evaluation

Likely Resolves by Q2 2027

Discussed by: Science Magazine, Washington Technology

NSF completes its re-evaluation of all four bids and formally reaffirms KBR as the awardee. The agency has already signaled it intends to keep KBR, saying it 'fully complied' with GAO's recommendations. The re-evaluation could take several months, and the current Leidos contract has been extended to September 2027 to allow for a transition.

2

Battelle Wins Contract on Re-Evaluation

Unlikely Resolves by Q2 2027

Discussed by: Battelle Memorial Institute

NSF's re-evaluation finds KBR's bid cannot be supported without the affiliate's experience, and awards the contract to Battelle or another bidder. This would be a major reversal for NSF, which has defended its original decision. GAO has said it is not telling NSF who should get the award, only that the evaluation should be redone correctly.

3

Battelle Files New Protest, Contract Delayed

Possible Resolves by Q1 2027

Discussed by: Washington Technology

Battelle challenges NSF's re-evaluation, filing a new protest with GAO. The contract remains in limbo while GAO reviews the new protest, potentially delaying the transition from the current contractor, Leidos. This would extend the dispute well into 2027.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

February-June 2008

Boeing tanker protest (2008)

The Air Force awarded a $35 billion tanker contract to Northrop Grumman and EADS in February 2008. Boeing protested, and GAO sustained the protest in June, finding the Air Force made significant errors in evaluating the bids.

Then

The Air Force canceled the award and re-competed the contract.

Now

Boeing won the re-compete in 2011, and the tanker program eventually delivered aircraft starting in 2024.

Why this matters now

Shows how a GAO-sustained protest can force a federal agency to re-evaluate and re-award a major contract, even when the agency initially defends its decision.

2019-2021

JEDI cloud contract (2019-2021)

The Pentagon awarded a $10 billion cloud computing contract to Microsoft in 2019. Amazon Web Services protested, and after a lengthy legal battle, the Pentagon canceled the contract in 2021 and started over.

Then

The original award was voided, and the Pentagon began a new procurement process.

Now

The contract was eventually split among multiple vendors, and the original single-award structure was abandoned.

Why this matters now

Illustrates how a protest can unravel a major federal contract award, even after the agency defends its decision through multiple rounds of litigation.

Sources

(10)