Jacobs to redesign DFW's Skylink guideway for Terminal F expansion

Jacobs to redesign DFW's Skylink guideway for Terminal F expansion

Built World

The design role puts Jacobs inside a $4 billion, 31-gate buildout that must keep the airport's driverless train running while aircraft lanes go in beneath it

Overview

Updated Yesterday

Dallas Fort Worth International Airport picked Jacobs on Nov. 24 to redesign the elevated guideway that carries Skylink, its driverless airport train. The redesign lets two parallel taxi lanes for aircraft run underneath, which is what makes room for up to 16 more gates at the airport's new Terminal F.

Skylink cannot stop. It is the secure-side link between terminals at an airport handling more than 87 million passengers a year, so every phase of the bridge work has to leave the train running. Jacobs is paired with Innovation Next+, the design-build joint venture already building Terminal F's concourse and station, to work out the construction sequence.

Why it matters

DFW is rebuilding the space under a train 87 million passengers a year depend on. The sequencing decides whether 16 gates open on time.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

$4B
Estimated cost of Terminal F
Airport estimate for the full 31-gate terminal and its connections.
31
Gates planned at Terminal F
Up from the 15 domestic gates in the original plan.
16
Gates the guideway changes unlock
Jacobs' work enables up to 16 additional gates beyond the first phase.
87 million
DFW annual passengers
Makes DFW one of the world's busiest airports.
$2.06B
Innovation Next+ contract ceiling
Covers the joint venture's Terminal F and Skylink station work, not Jacobs' design fee.
6
Station modules lifted into place
Each weighed 210 to 310 tons and took roughly eight overnight hours to set.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

2024 November 2026

7 events Latest: Yesterday
Tap a bar to jump to that date
  1. Jacobs wins design role for Skylink guideway changes

    Latest Contract

    DFW announced on Nov. 24 that it selected Jacobs to alter the guideway bridge spans so two taxi lanes can pass beneath, without halting the train.

  2. All six Terminal F station modules lifted into place

    Construction

    Crews hoisted modules weighing 210 to 310 tons each during controlled overnight windows, about eight hours per lift.

  3. Board clears design work on Skylink column modifications

    Approval

    The authorization let structural design advance alongside fit-out and apron paving, and lifted the contract ceiling by up to $300 million to about $2.06 billion.

  4. Skylink runs overnight track closures for station work

    Operations

    DFW shut a section of track overnight while keeping every station reachable, an early look at the service constraints ahead.

  5. Board adds $582 million and 379 days to the Terminal F contract

    Contract

    The action raised Innovation Next+'s contract ceiling and extended its completion period as the terminal's scope expanded.

  6. Terminal F grows from 15 domestic gates to 31

    Scope change

    American Airlines and DFW extended their lease agreement and re-scoped the terminal for international flights and widebody aircraft.

  7. DFW picks Innovation Next+ to build Terminal F

    Contract

    The joint venture won an $855 million contract for a 400,000-square-foot concourse and a Skylink station, designed to allow later additions.

Scenarios

1

First 15 Terminal F gates open in 2027

Likely Resolves by End of 2027

Discussed by: DFW's Nov. 3 construction update and its April 2 board agenda

Airport records lay out a staggered opening: 10 gates in May 2027, five more by the end of that year, with the remaining 16 to follow in later phases. Hitting it depends on fit-out, apron paving and the guideway work proceeding without a stop-work order. DFW has not said when the final 16 gates become operational.

2

Terminal F cost passes $4 billion

Possible Resolves by Aug 29, 2028

Discussed by: Board contract amendments reported by Engineering News-Record and the American Trades Index

Terminal F was estimated at $4 billion on a 31-gate scope that itself replaced a smaller 15-gate plan. The joint venture's ceiling has already risen twice through amendments, with unpriced remaining scope tracked on a time-and-materials basis until costs are agreed. Further scope growth or guideway complications would push the total past the current estimate.

3

All 31 Terminal F gates in service by the 2028 contract date

Unlikely Resolves by End of 2028

Discussed by: Engineering News-Record, citing the airport's contract completion date

The Innovation Next+ contract carries an Aug. 29, 2028 completion date. That date does not establish when all 31 gates open, and airport statements describe the last 16 as following in subsequent phases. A full buildout by that date would require the guideway work, station integration and terminal fit-out to finish without slippage.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

1994-1995

Denver International Airport's automated baggage system (1994-1995)

Denver's new airport was built around an automated baggage system meant to speed transfers. The system jammed repeatedly in testing while the rest of the airport sat finished, and the opening slipped month after month.

Then

The airport opened on Feb. 28, 1995, roughly 16 months behind its original date.

Now

The baggage system was later abandoned, and airport planners began treating automation inside a live build as the schedule's critical path.

Why this matters now

DFW faces the same structure of risk with a train instead of a baggage belt: an automated system that must keep working while the structure holding it is rebuilt.

March 2008

Heathrow Terminal 5 phased opening (2008)

Heathrow opened Terminal 5 in stages, moving British Airways in over months so the rest of the airport could keep operating. The first days brought baggage failures, long queues and cancelled flights.

Then

The airport and airline apologized publicly and spent weeks fixing baggage handling and staffing.

Now

Staged terminal moves became standard practice at large hub airports, with each phase tested before the next.

Why this matters now

Terminal F is also opening in slices, 10 gates then five, which spreads risk but leaves the airport exposed at each handover.