Jacobs wins delivery role on AEP's seven-state transmission build

Jacobs wins delivery role on AEP's seven-state transmission build

Built World

The Dallas contractor will run program delivery on a $37 billion portfolio, most of it recovered through customer rates.

Overview

Updated 2 hours ago

American Electric Power selected Jacobs to manage delivery of the eastern half of a $37 billion transmission program, the companies said Oct. 29. Jacobs will handle project controls, engineering, siting, right-of-way acquisition and environmental review across seven states for five years. WSP USA holds the matching role across four western states.

The award is a management layer over a much larger build. AEP expects its transmission rate base to climb from about $37 billion this year to $69 billion by 2031, with 92% of its newly contracted load tied to data centers. Because most transmission spending is recovered through customer rates, the schedule Jacobs keeps will show up on household bills in Indiana, Ohio, Michigan, Kentucky, Tennessee, West Virginia and Virginia.

Why it matters

Most of AEP's $37 billion transmission build is recovered through customer rates, so Jacobs' delivery schedule lands on seven states' electric bills.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

$37B
AEP's planned transmission investment over five years
Spans 11 states; Jacobs handles the seven-state eastern half, WSP the four-state west.
7
States in Jacobs' portfolio
Indiana, Michigan, Ohio, Kentucky, Tennessee, West Virginia and Virginia.
$100B
AEP's capital plan for 2027 through 2031
Transmission is the largest slice, ahead of about $36 billion for generation.
92%
Share of AEP's contracted load tied to data centers
AEP expects 84 GW of incremental contracted load by 2031, crypto customers included.
$69B
Projected transmission rate base in 2031
Up from roughly $37 billion in 2026, according to the utility's investor presentation.
$5B
Cost of the Piketon, Ohio 765-kV project
Serves SB Energy's planned 10.4-GW data center campus on a former federal enrichment site.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

March 2026 November 2026

6 events Latest: Today
Tap a bar to jump to that date
  1. AEP creates AEP Infrastructure business unit

    Today Corporate structure

    The unit combines competitive generation, infrastructure development and retail and wholesale energy, led by Greg Hall.

  2. AEP picks Jacobs for east, WSP for west

    Contract award

    Jacobs takes integrated delivery across seven states for five years; WSP USA takes the four-state western portfolio.

  3. AEP lifts five-year capital plan to $100 billion

    Corporate strategy

    The 2027-2031 plan puts about $37 billion into transmission. AEP also reported 15 GW of new load commitments signed in the third quarter.

  4. Energy Department finalizes $1.6 billion loan guarantee for AEP

    Federal action

    The guarantee backs reconductoring and rebuilding 5,000 miles of high-voltage line across five states, part of a $3.56 billion program.

  5. Ratepayers rally in Ironton, Ohio, over grid costs

    Protest

    Residents demonstrated against data-center-driven grid spending and the electricity rates that follow it.

  6. Ohio regulators raise AEP Ohio transmission charges

    Regulation

    State regulators approved higher transmission charges, about $7.90 a month for a household using 1,000 kilowatt-hours.

Scenarios

1

Piketon lines break ground in the first quarter of 2027

Likely Resolves by Q2 2027

Discussed by: AEP management on its Oct. 28 earnings call and in its quarterly SEC filing

AEP says it has secured substantially all rights-of-way and finalized commercial agreements for the three 765-kV lines serving SB Energy's campus. Construction is expected to start in the first quarter of 2027, contingent on approvals from PJM, the Public Utilities Commission of Ohio and the Federal Energy Regulatory Commission. Slippage in any of those dockets pushes the 2028, 2029 and 2030 in-service targets.

2

A regulator disallows part of the transmission spend from rates

Possible Resolves by End of 2027

Discussed by: The Ohio Consumers' Counsel and ratepayer groups in the seven states

About $28 billion of the $37 billion is regional-planning and reliability spending recovered through rates, rather than billed to a single large customer. Consumer advocates have already contested AEP Ohio transmission charges. A commission that rules part of the investment imprudent would move that cost onto shareholders and reset the economics of the delivery contracts Jacobs and WSP are staffing up for.

3

AEP trims the capital plan as data-center demand slips

Possible Resolves by End of 2027

Discussed by: AEP's own filings, which flag that projected data-center demand may not materialize as expected

AEP signed 15 GW of new load commitments in a single quarter and expects 84 GW of incremental contracted load by 2031. That pipeline is the justification for nearly doubling the transmission rate base. A slower signing pace, a customer default, or a delay at a single large campus would give regulators and investors a reason to ask AEP to stretch the schedule rather than build ahead of demand.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

Late 1960s

AEP and the first 765-kilovolt lines (late 1960s)

AEP energized the first 765-kilovolt transmission in the United States, a voltage class that moves far more power per line than the 345-kilovolt circuits it replaced. The company built those lines across the Ohio Valley and has kept the lead: it now owns about 90% of the nation's existing 765-kV mileage.

Then

The extra-high-voltage backbone let AEP move power between its own generating stations and neighboring systems at a scale smaller utilities could not match.

Now

That network became the platform every subsequent AEP transmission expansion extends, and the reason a single utility can now plan a near-tripling of 765-kV mileage.

Why this matters now

The Piketon project is three more 765-kV lines on the same backbone, each adding roughly 3.2 GW of capacity.

2008-2014

Texas competitive renewable energy zones (2008-2014)

Texas regulators designated wind-rich areas of West Texas as competitive renewable energy zones, then approved a multibillion-dollar transmission build to carry that output toward Dallas, Austin and San Antonio. The lines were planned in advance of the generation, not after it.

Then

Wind developers built into a grid with room for them, and curtailment in the region fell.

Now

The build became the reference case for planning transmission around expected demand rather than waiting for congestion to prove the need.

Why this matters now

AEP's program runs the opposite way: the Piketon lines are sized for one customer's campus, with that customer paying, while most of the remaining spend waits on regional planning and state approvals.