Wison starts building ADNOC Gas's Habshan 7 gas processing train

Wison starts building ADNOC Gas's Habshan 7 gas processing train

Built World

A $3.9 billion contract, the largest in Wison's history, moves from engineering into site work, with start-up targeted for 2029

Overview

Updated 1 hour ago

Wison Engineering held a groundbreaking ceremony at Habshan on 11 November 2026 for a new gas processing train, moving its $3.9 billion contract into site construction. It is the largest engineering, procurement and construction (EPC) award in the company's history, and with an accompanying 220-kilovolt switch station the total comes to about $4.04 billion.

The train is one of two awarded on 10 August 2026, when ADNOC Gas took final investment decisions on the second and third phases of its $13.2 billion Rich Gas Development. ADNOC Gas says the Habshan unit will process 670 million cubic feet of gas a day, strip out liquids such as ethane and propane for petrochemical feedstock, and be finished in 2029.

Why it matters

Abu Dhabi is adding gas liquids capacity that feeds plastics and chemicals worldwide; whether the 2029 start-up date holds is the open question.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

$3.9B
Wison's Habshan EPC contract
Base contract value for the new gas processing train, awarded in August 2026.
$4.04B
Contract including switch station
Total value once the associated 220-kilovolt electrical switch station is counted.
$13.2B
Rich Gas Development, all three phases
ADNOC Gas's largest-ever capital investment, spread across Habshan, Asab, Bu Hasa, Das Island and Ruwais.
670 MMcfd
Design gas processing capacity
Figure given by ADNOC Gas; Wison has not published its own capacity number.
60%
ADNOC Gas EBITDA growth target by 2030
Company target cited by chief executive Fatema Al Nuaimi when announcing the phase 2 and 3 awards.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

June 2025 November 2026

7 events Latest: Today
Tap a bar to jump to that date
  1. Trade press reports the groundbreaking

    Today Report

    Construction Review reports the 11 November ceremony and the project's place in the $13.2 billion programme.

  2. Wison publishes ceremony notice

    Statement

    Company says engineering, procurement and site preparation have advanced since August.

  3. Habshan 7 groundbreaking ceremony

    Construction

    Wison and ADNOC Gas mark the start of full site construction in Abu Dhabi.

  4. Ruwais construction starts

    Construction

    Tecnimont begins site work on the fifth natural gas liquids fractionation train at Ruwais.

  5. Wison confirms largest-ever award

    Contract

    Wison announces the $3.9 billion Habshan contract plus switch station, about $4.04 billion in total.

  6. Phases 2 and 3 approved, $8.2 billion awarded

    Contract

    ADNOC Gas takes FIDs on the next two phases and awards contracts to Wison and Tecnimont.

  7. ADNOC Gas sanctions first phase

    Investment

    Final investment decision on $5 billion of upgrades at Asab, Bu Hasa, Habshan and Das Island, targeted for 2027.

Scenarios

1

Habshan 7 starts up in 2029 as scheduled

Possible Resolves by End of 2029

Discussed by: ADNOC Gas, which named 2029 as the completion year when it announced the award; Wison has published no completion date of its own.

Site work ramps up through 2027 and 2028, commissioning follows, and ADNOC Gas announces first gas in 2029. The trigger is steady progress with no disclosed contract variation. Neither company has published a quarterly milestone schedule, so the visible checkpoints are Wison's project updates and its annual reports.

2

Wison discloses a cost increase or a delay on Habshan 7

Possible Resolves by End of 2028

Discussed by: No company forecast; both firms describe the project as on schedule. Cost and schedule slippage is the common outcome for gas processing megaprojects.

A revised contract value or a new completion date appears in a Hong Kong stock exchange filing or an ADNOC Gas statement. Possible triggers are scope changes, labour and supply-chain costs, or site conditions at Habshan. The contract was signed in August 2026, so any variation would surface early in construction.

3

ADNOC Gas adds a fourth phase beyond the three announced

Unlikely Resolves by End of 2028

Discussed by: ADNOC Gas, which told investors in August that the programme can handle associated gas from 5 million barrels a day of oil output, leaving room above current plans.

ADNOC Gas approves another processing train or fractionation unit, extending the buildout past the $13.2 billion already committed. The company calls the programme its largest-ever capital investment and ties it to 60% EBITDA growth by 2030, which gives it a reason to keep adding capacity if gas volumes rise.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

September 2013

Kashagan, Kazakhstan (2013)

A consortium including Eni, Shell and ExxonMobil brought the North Caspian project to first oil in September 2013, roughly eight years after the original 2005 start date. The field had already absorbed repeated budget blowouts and management changes before any barrel shipped.

Then

Production stopped within weeks because of pipeline leaks and did not resume until 2016.

Now

The partners renegotiated terms with the Kazakh government, and the project became the standard cautionary case for Caspian megaprojects.

Why this matters now

It shows how a technically ambitious, multi-company project can lose years after construction begins, which is the main risk hanging over the 2029 Habshan date.

2009-2016

Gorgon LNG, Australia (2009-2016)

Chevron approved the Gorgon gas project on Barrow Island in 2009 at a budget of about A$43 billion. The first cargo left in March 2016, roughly two years behind the original plan, with final costs billions of dollars above the approved figure.

Then

Chevron booked impairments and its carbon capture component ran years behind the rest of the plant.

Now

Gorgon became the reference case for Australian LNG cost inflation, and buyers began demanding firmer delivery schedules.

Why this matters now

Large gas processing trains routinely slip, and ADNOC Gas's 2029 date for Habshan 7 has not yet been tested by construction.