Kashagan, Kazakhstan (2013)
A consortium including Eni, Shell and ExxonMobil brought the North Caspian project to first oil in September 2013, roughly eight years after the original 2005 start date. The field had already absorbed repeated budget blowouts and management changes before any barrel shipped.
Production stopped within weeks because of pipeline leaks and did not resume until 2016.
The partners renegotiated terms with the Kazakh government, and the project became the standard cautionary case for Caspian megaprojects.
It shows how a technically ambitious, multi-company project can lose years after construction begins, which is the main risk hanging over the 2029 Habshan date.