Calcasieu Pass (2022-2025)
Venture Global's first LNG terminal went from final investment decision to first LNG in 29 months, faster than any comparable project. But the plant then spent another 38 months in commissioning, producing and exporting cargoes that were sold on the spot market rather than delivered to the buyers holding long-term contracts.
Contract customers waited years for volumes they had already agreed to buy, and some pursued arbitration.
The gap between first LNG and commercial operations became the central criticism of Venture Global's construction model.
Plaquemines ran the same playbook, with a 22-month commissioning window. Its 53-month FID-to-COD timeline is the company's answer to that criticism.