Caisson permit issued for Carter Cadillac dealership near Lincoln Yards

Caisson permit issued for Carter Cadillac dealership near Lincoln Yards

Built World Chicago, IL local

The parcel Sterling Bay bought in 2018 for a medical office building will hold a two-story showroom and a six-story, 490-space garage, with an opening targeted for late 2027.

Overview

Updated 1 hour ago

Sterling Bay bought 1400 W. North in 2018 and planned a five-story, 100,000-square-foot medical office building on it. On Nov. 28, a caisson permit was issued for what is actually being built there: Carter Cadillac of Chicago, a two-story showroom with a six-story, 490-space parking garage attached.

The caisson permit covers foundation work, not the finished building; a full building permit was still pending as of May. But the project shows what is replacing the megaproject around it. Sterling Bay's $6 billion, 55-acre Lincoln Yards plan stalled as the office market failed, and JDL Development now holds the northern half while Novak Construction holds the southern half.

Why it matters

Chicago's largest failed megaproject is refilling one parcel at a time, with a car dealership where 600-foot towers were planned.

Last Monday's email for Chicago, IL

Sent Nov 23. It carried:

Get next Monday's: one short email a week. Free. Unsubscribe in one click.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

$15.5M
Price Jack Carter Automotive Group paid Sterling Bay for the parcel
Recorded in December 2025, according to county records cited by the Chicago Tribune.
490
Parking spaces in the attached six-story garage
Spaces are for inventory and customer vehicles.
$6B
Sterling Bay's estimated cost for the full Lincoln Yards plan
The plan called for towers up to 600 feet, thousands of homes, and riverfront parks.
$34M
Price Novak Construction paid for Lincoln Yards' southern half
The January 2026 sale split the site between two new owners.
1
Cadillac dealerships that would operate inside Chicago
The brand's remaining Chicago-area stores are in Lincolnwood, Oak Lawn, and Northbrook.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

2018 November 2026

7 events Latest: Today
Tap a bar to jump to that date
  1. Caisson permit issued for the dealership

    Today Permit

    Foundation work can proceed on the two-story showroom and six-story, 490-space garage.

  2. Groundbreaking for Carter Cadillac of Chicago

    Construction

    Officials celebrate the start of work; a full building permit is still awaiting issuance.

  3. City Council approves Foundry Park

    Approval

    The Council signs off on JDL's replacement for the northern half of Sterling Bay's plan.

  4. Plan Commission approves Foundry Park; Novak buys the south half

    Approval

    JDL's smaller residential plan advances as Novak Construction pays $34 million for Lincoln Yards' southern half.

  5. Jack Carter Automotive Group buys 1400 W. North

    Acquisition

    The dealer group pays Sterling Bay $15.5 million for the vacant parcel, according to county records.

  6. JDL Development takes Lincoln Yards' northern half

    Ownership change

    A Chicago builder steps in as Sterling Bay's control of the megaproject unravels.

  7. Sterling Bay buys the parcel for a medical office building

    Acquisition

    The developer planned a five-story, 100,000-square-foot medical office building at 1400 W. North, next to its Lincoln Yards site.

Scenarios

1

Carter Cadillac opens on West North Avenue in late 2027

Likely Resolves by End of 2027

Discussed by: Jack Carter Automotive Group and Urbanize Chicago, which both give a late-2027 opening target

Caisson work proceeds, the city issues the full building permit, and the showroom and garage are finished on the schedule the developer has given. This is the base case: the parcel is bought, the groundbreaking has happened, and the foundation permit is in hand.

2

Foundation work finishes but the full building permit slips

Possible Resolves by Q2 2027

Discussed by: Implied by the May 2026 groundbreaking report, which noted a full building permit was still pending months after work was celebrated

Caisson crews complete the deep foundation and then stop, because the full building permit needed for vertical construction has not been issued. The site sits with foundation work done and nothing above grade, pushing the opening past the developer's late-2027 target.

3

Car dealers and retailers replace the megaproject parcel by parcel

Possible Resolves by End of 2028

Discussed by: Alderman Scott Waguespack, who said businesses from small manufacturers to clothing and food retailers are asking about the area

The Cadillac store turns out to be the template rather than an exception. Other Sterling Bay parcels go to auto, retail, or light-industrial users instead of a unified office and life sciences district, and Lincoln Yards ends up as a patchwork of separate low-rise projects.

Historical Context

3 moments from history that rhyme with this story — and how they unfolded.

2007–2010

Chicago Spire (2007–2010)

Developer Garrett Kelleher proposed a 150-story Santiago Calatrava tower at 400 N. Lake Shore Drive. Work started in 2007 and stopped in 2008 when financing dried up, leaving a foundation and an empty site on the lakefront.

Then

Kelleher's firm defaulted and the parcel sat unfinished for years.

Now

Related Midwest took over the land and later began a smaller two-tower plan on the same ground.

Why this matters now

Lincoln Yards followed the same path: a grand plan undone by financing and demand, with the land later absorbed by more modest projects.

November 2018 – February 2019

Amazon HQ2 in Long Island City (2018–2019)

Amazon chose Long Island City for half of its second headquarters in November 2018, with New York State and City offering roughly $3 billion in incentives. After sustained local opposition, the company canceled the plan in February 2019.

Then

The promised campus never arrived and the incentives went unused.

Now

The neighborhood kept building housing and offices in smaller, separate projects rather than one corporate district.

Why this matters now

It shows how fast a negotiated mega-plan can dissolve, and how the land then gets filled by ordinary development.

1988–2024

Michigan Central Station (1988–2024)

Detroit's 1913 train station closed in 1988 and sat vacant and stripped for three decades. Ford Motor Company bought the building in 2018 and restored it as a mobility research campus.

Then

The building reopened in June 2024 as Ford's Michigan Central innovation hub.

Now

A single committed corporate user replaced the mixed-use district planners had imagined for the site.

Why this matters now

A long-vacant parcel finding one committed user is what is happening at 1400 W. North, where a car dealer is the first taker.