US data center cancellations more than double as local governments block projects

US data center cancellations more than double as local governments block projects

Built World

Sixteen projects were stopped in the third quarter, and voters in ten states have now approved measures limiting construction

Overview

Updated 26 minutes ago

Sixteen planned data centers were stopped in the United States between July and September, more than double the seven halted in the same quarter of 2025. Since 2024, 70 projects carrying an estimated $271 billion in announced investment have been blocked, withdrawn or stalled.

The fights are local, and the votes are binding. Relae counted 46 of 47 local ballot measures restricting data center development passing in the November 3 election, and an NBC exit poll it cited found 76% of voters opposed new data centers in their own communities.

Why it matters

A cancelled project leaves utilities with planned power plants, towns with budgeted tax revenue, and developers with land they cannot use.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

So, are all these cancellations going to impact the capex that the big hyperscalers have said they're going to spend?

Not in the near term: hyperscaler capex guidance is still climbing and most 2027 capacity is already under construction, but the backlash is likely to shift where—and how much—gets built from 2028 onward.

If post-2028 projects stall, the $1 trillion AI investment cycle could concentrate in friendly states or move abroad, raising power and permitting costs for everyone.

4 details6 sources2 disagreements
  • BofA Global Research sees hyperscaler capex growing more than 90% in 2026 and still up 35% in 2027 — guidance has not been cut.
  • Nomura says capacity due online in 2027 is already under construction, limiting near-term impact; 2028 projects face the permitting and regulatory risk.
  • Neuberger Berman expects capex estimates to keep rising: big cloud providers and model developers are locking in land, power and buildings now, and deciding on chips later.
  • J.P. Morgan notes under-construction capacity grew nearly 50% in H1 2026, while Wood Mackenzie finds only 59% of 430 GW of proposed capacity is under active development — many cancellations are plans, not shovels.
Room for disagreement
  • Optimists at J.P. Morgan, BofA and Baird's Justin Hauke say economic incentives keep states accommodating development, most restrictions are temporary, and this is not a fundamental derailing of a generational investment cycle.
  • Pessimists point to more than $260 billion in cancelled projects this year, S&P data tying 77% of delayed projects to local opposition, and newly elected governors in Texas, Ohio and Georgia who campaigned on restrictions — a real supply-side hit starting 2028.
0 AI answers with web search. May be wrong.

Key Indicators

16
Projects cancelled in Q3 2026
Up from seven in the same quarter of 2025, according to Relae's tracker.
$271B
Investment blocked, withdrawn or stalled since 2024
Estimated or announced capital across 70 stopped projects.
$64B
Investment stopped in Q3 2026 alone
Relae's estimate of planned spending halted in the quarter.
76%
Voters opposing new data centers in their community
NBC exit poll figure cited by Relae.
46
Local ballot measures restricting data centers that passed, of 47
Relae's count for the November 3 election.
182
Projects delayed or cancelled, per S&P Global
The firm ties 77% of them to local opposition.

Voices

Curated perspectives — historical figures and your fellow readers.

Ayn Rand

Ayn Rand

(1905-1982) · Cold War · philosophy

Fictional AI pastiche — not real quote.

"The mob has spoken, and as always, it votes to cut the throat of the very force that sustains its existence. These data centers are the cathedrals of the modern age, built by the rational minds that the parasites now condemn to starvation, yet they celebrate their own descent into the primitive darkness with a self-righteous ballot."

Sign up to generate historical perspectives on this story.

Organizations Involved

Timeline

2024 November 2026

6 events Latest: Today
Tap a bar to jump to that date
  1. Q3 cancellations more than double to 16

    Today Data

    Relae's tracker counted 16 projects stopped in the third quarter, up from seven a year earlier, and $64 billion in halted investment. Five were developer withdrawals.

  2. Voters in ten states back data center limits

    Election

    Forty of 41 local restrictive measures passed, per ENR; Relae counted 46 of 47. Trenton, Ohio approved its ban with about 80% support.

  3. Relae publishes opposition study

    Report

    Relae analyzed 46 opposed projects and put lost announced investment above $170 billion. It found host communities were demographically close to the US median.

  4. Cancellations quadruple to 25

    Data

    Twenty-five projects were cancelled in 2025, 21 of them in the second half. Developer withdrawal before a formal vote became the most common outcome.

  5. Six US data center projects cancelled

    Data

    Relae's baseline year: six AI data center projects were cancelled in the United States.

Scenarios

1

Cancellations keep climbing through 2027

Likely Resolves by Aug 31, 2027

Discussed by: Relae, whose July 2026 report called local opposition a predictable feature of the AI infrastructure landscape

Relae's framing is that opposition is now structural, not episodic: transparency failures are the top community complaint, and developers still negotiate benefits late in permitting. If that holds, quarterly counts stay in double digits. A wave of early community benefit agreements could break the pattern.

2

A state strips local governments of zoning power

Possible Resolves by End of 2027

Discussed by: Utility Dive, citing energy analytics firm Orennia, and reporting on incoming governors in Texas, Ohio and Georgia

Developers and utilities argue a county-by-county approval process cannot deliver the capacity grids need. Incoming governors in three large data center states campaigned on restricting construction, but states can also preempt local bans, and a single preemption law would reset the map.

3

Utilities pull back planned capacity

Possible Resolves by Q2 2027

Discussed by: Orennia, in a report covered by Utility Dive

Utilities filed generation and transmission plans assuming gigawatts of data center load would materialize. Orennia warned that planned capacity now carries new risk, concentrated in Texas, Ohio and Georgia. If enough projects die, regulators will see requests to cut forecasts or shift costs to other ratepayers.

Historical Context

3 moments from history that rhyme with this story — and how they unfolded.

November 2018 - February 2019

Amazon HQ2 in Long Island City (2018-2019)

Amazon picked New York City and Arlington, Virginia for its second headquarters after a 14-month contest among 238 cities. The New York deal carried roughly $3 billion in state and city incentives. Local politicians and unions opposed it within weeks.

Then

Amazon cancelled the Long Island City campus in February 2019 and delivered none of the promised jobs there.

Now

Amazon expanded in New York anyway with leased offices, and the episode became a model for how local coalitions can veto a project regardless of subsidy size.

Why this matters now

Shows that opposition can kill a project even when the economic case is strong, and that companies often regroup rather than leave a market.

2001 - 2017

Cape Wind (2001-2017)

A developer proposed 130 wind turbines in Nantucket Sound. Federal regulators approved the project in 2010 after a decade of review. Wealthy waterfront homeowners, including members of the Kennedy and Koch families, fought it throughout.

Then

The project lost its power purchase agreements by 2015 as opposition and litigation drained it.

Now

The developer surrendered the lease in 2017. Nothing was built, despite full federal approval.

Why this matters now

A siting fight can run for more than a decade and end with zero construction, even after the permits are granted.

1974 - 1989

US nuclear construction cancellations (1970s-1980s)

Utilities ordered a wave of nuclear reactors, then cancelled dozens of them as construction costs rose, demand forecasts fell, and public opposition hardened after the 1979 Three Mile Island accident.

Then

Utilities wrote off large sums and some never recovered financially.

Now

No new US reactor started construction for decades, and the industry's cost estimates lost credibility with regulators.

Why this matters now

An infrastructure buildout can reverse at scale when siting fights and cost overruns arrive together, which is the risk now facing data center construction.