Hillwood adds two speculative warehouses at AllianceTexas

Hillwood adds two speculative warehouses at AllianceTexas

Built World Fort Worth, TX local

The Fort Worth developer starts 354,593 square feet of tenant-free industrial space as its AllianceTexas pipeline reaches 8.9 million square feet

Overview

Updated 2 hours ago

Hillwood said on November 19 that it will build two warehouses in Haslet, Texas, together totaling 354,593 square feet, with construction starting in December. Neither building has a tenant — both are speculative, put up on the bet that a logistics or manufacturing company signs a lease before the roof is finished.

The two buildings are the small end of a much larger program. As of October, Hillwood had 8.9 million square feet of industrial space under construction or in design at AllianceTexas, the 27,000-acre development it has run north of Fort Worth since 1989. In June the total was 8.2 million square feet, with 6.8 million of it under construction. By October, 5.9 million was under construction and 3 million sat in design, so the pipeline grew while more of it moved back onto the drawing board.

Why it matters

Roughly 8.9 million square feet of warehouse space is moving through one Texas development, a bet that freight and manufacturing demand holds into 2028.

Last Monday's email for Fort Worth, TX

Sent Nov 16. It carried:

Get next Monday's: one short email a week. Free. Unsubscribe in one click.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

354,593 sq ft
New speculative space announced
Alliance Westport 41 and 42, combined, with construction starting in December 2026.
8.9M sq ft
AllianceTexas industrial pipeline
Under construction or in design as of October 2026, per Hillwood.
5.9M sq ft
Under construction
Down from 6.8 million square feet reported in June 2026.
73,000
Direct jobs at AllianceTexas
Hillwood's count of jobs created by the 600-plus companies at the development.
$142.9B
Cumulative regional economic impact
Hillwood's estimate for North Texas since 1989.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

1989 November 2026

7 events Latest: Yesterday
Tap a bar to jump to that date
  1. Two Haslet buildings announced

    Latest Announcement

    Alliance Westport 41 and 42, totaling 354,593 square feet, with construction set for December.

  2. Pipeline reaches 8.9 million square feet

    Data point

    Hillwood counts 5.9 million under construction and 3 million in design.

  3. 1.21-million-square-foot Westport 16 announced

    Announcement

    Pipeline reaches 8.2 million square feet, with 6.8 million under construction.

  4. Hillwood announces largest speculative round yet

    Announcement

    Five buildings totaling 3.1 million square feet under construction, plus 2.6 million in predevelopment.

  5. Gateway 70 and 71 construction starts

    Construction

    Work begins on the two Independence Parkway buildings announced the following month.

  6. Alliance Westport 14 completed

    Construction

    The building is later named as one of two AI manufacturing sites for Wistron.

  7. AllianceTexas development begins

    Development

    Hillwood starts building the 27,000-acre project around Perot Field Fort Worth Alliance Airport.

Scenarios

1

Construction on Westport 41 and 42 begins in December 2026 as planned

Likely Resolves by Feb 28, 2027

Discussed by: Hillwood's own announcement, reported by the Fort Worth Business Press and Fort Worth Inc.

Hillwood said construction is expected to begin in December 2026. A start on both buildings, or news of a delay, would show whether the company can keep its stated pace as the pipeline shifts toward early-stage design work.

2

A tenant signs for one of the Haslet buildings before completion

Possible Resolves by End of 2027

Discussed by: Hillwood, which describes its speculative program as a way to have space ready when tenants commit

The buildings are pitched at logistics and manufacturing companies that want 150,000 to 200,000 square feet near the rail yard. A signed lease before the August 2027 target completion would validate the spec model at this smaller size; no announcement would leave both buildings empty into 2028.

3

Hillwood's AllianceTexas pipeline passes 10 million square feet

Uncertain Resolves by End of 2027

Discussed by: No public forecast; derived from the growth from 8.2 million square feet in June 2026 to 8.9 million in October

The pipeline grew 700,000 square feet in four months even as the under-construction share fell. If Hillwood keeps announcing new buildings at that rate, the total would cross 10 million square feet during 2027. A flat or shrinking figure would suggest the company is waiting for tenants to catch up with what it has already built.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

1989

AllianceTexas breaks ground (1989)

Hillwood began developing 27,000 acres north of Fort Worth around a new airfield, Perot Field Fort Worth Alliance Airport, which the company describes as the world's first dedicated industrial airport. A BNSF intermodal yard followed, giving tenants rail and air freight on the same site. The project now holds about 64.7 million square feet of commercial space and more than 600 companies.

Then

The airport and rail yard gave the site a freight advantage that ordinary industrial parks could not match.

Now

Hillwood puts the cumulative regional economic impact at $142.9 billion since 1989 and counts about 73,000 direct jobs at the development.

Why this matters now

The two new buildings are cheap to justify because the expensive infrastructure — runway, rail yard, highway access, foreign-trade zone — is already there.

July 2025

Alliance Westport 14 fills with an AI manufacturer (2025)

Hillwood completed Alliance Westport 14 as a speculative building. Wistron, one of the world's largest electronics manufacturers, then announced two AI advanced-manufacturing facilities at AllianceTexas, one of them in that building.

Then

A tenant-free building became a named advanced-manufacturing site without a ground-up build for the occupant.

Now

Hillwood now cites Wistron, along with Southwire and SGS Studios, as proof that speculative buildings can be adapted for large tenants after the fact.

Why this matters now

It is the template for the November announcement: build first, fit out later, and let the tenant's schedule set the terms.