Google pauses Belgian data centre after Wallonia finds building outside its permit

Google pauses Belgian data centre after Wallonia finds building outside its permit

Built World

A 2024 permit covers three air-cooled halls. Google built one three-hectare hall cooled by river water, and inspectors stopped the site on 26 November.

Overview

Updated 42 minutes ago

The structural work on a three-hectare data centre hall at Farciennes is done. On 26 November, Walloon inspectors found the building did not match the permit Google can legally build under, and ordered the roughly 300 workers on site to stop.

Google's valid permit, granted in 2024, covers three smaller halls cooled by air. In 2025 it asked to merge two of them into one larger building and draw cooling water from the Sambre river. The regional minister refused that change in August, and Belgium's Council of State hears Google's appeal on 7 January.

Why it matters

Wallonia has shown a building erected ahead of its permit can be halted mid-project, testing whether planning appeals can keep pace with data-centre construction.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

3 hectares
Building footprint flagged by inspectors
The hall is larger than anything the valid 2024 permit allows.
600 m³/h
Cooling water sought from the Sambre
Planned draw under the 2025 modification, as reported by The Guardian.
~300
Workers on site at the inspection
Headcount on 26 November, when the verbal stop order was issued.
53 hectares
Total site area
The Ecopôle park straddles Farciennes, Aiseau-Presles and Sambreville.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

2024 November 2026

10 events Latest: Today
Tap a bar to jump to that date
  1. Google says the works are suspended

    Today Statement

    The company says recent activity was site maintenance and security, and cites valid permits.

  2. Wallonia orders checks on the site

    Statement

    The minister's office says the 2024 permit stands and officers will inspect.

  3. Minister refuses the modification

    Decision

    François Desquesnes cites the data centre's water needs during a historic drought.

  4. Walloon administration approves the modification

    Permit

    Regional officials clear the larger, water-cooled design.

  5. Google asks to build bigger and use river water

    Permit

    The modification merges two halls into one and switches cooling to the Sambre.

  6. Wallonia grants Google its original permit

    Permit

    Permission covers three smaller data centres at Ecopôle, cooled by air.

Scenarios

1

Council of State suspends the refusal and Google resumes the larger hall

Possible Resolves by Q1 2027

Discussed by: RTBF, which reports Google is seeking suspension of the ministerial decision alongside annulment

A suspension would restore the 2025 plans while the full case is argued, and the halted three-hectare building would match a live permit again. Google requested exactly that on 17 October and the court hears the request on 7 January. Belgian administrative courts can rule on suspension faster than on annulment, so a decision is plausible in the first quarter of 2027.

2

Google falls back on the 2024 permit and builds three air-cooled halls

Possible Resolves by Q2 2027

Discussed by: Walloon officials, who told RTBF the 2024 permit remains valid and that building to those plans is lawful

If the refusal stands, Google's only clean path is the original permission: three smaller halls cooled by air, no Sambre water draw. That means reworking a site where one much larger building is already framed. The company has not said whether it will do this, and the appeal gives it a reason to wait.

3

Prosecutors open a case over the unpermitted construction

Unlikely Resolves by Q2 2027

Discussed by: Walloon officials, who said a formal offence report would go to the public prosecutor's office

Belgian inspectors record offences in a formal report (a procès-verbal) and pass it to prosecutors, who then decide whether to act. The regional official Raphaël Stokis described the finding as a major offence: an illegal building covering three hectares. This track runs separately from the planning appeal and could outlast it.

4

Google abandons Farciennes

Unlikely Resolves by End of 2027

Discussed by: No party to the dispute has raised this; it is the outcome Apple chose in Ireland in 2018

Google has already spent heavily on the site, which makes walking away expensive. But a long court fight plus an enforcement file raises the cost of staying, and hyperscale operators have scrapped European projects before rather than keep paying for land they cannot use. Google has given no indication it is considering this.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

February 2015 - May 2018

Apple's Athenry data centre (2015-2018)

Apple announced an €850 million data centre in County Galway in 2015 and won planning permission in 2016. Objections sent the approval into the Irish courts, and the case ran for more than a year before the company gave up.

Then

Apple scrapped the project in 2018 and moved the workload to Denmark instead.

Now

The case became the standard example of how planning litigation can cost a country an investment without any regulator ever saying no.

Why this matters now

Farciennes shows the mirror image: Google built first and the permit fight caught up with it, where Apple waited and then left.

February 2020 - March 2022

Tesla's Grünheide factory (2020-2022)

Tesla began clearing forest and pouring foundations in Brandenburg under preliminary approvals, before the final environmental permit existed. Environmental groups complained, and a court temporarily halted tree-clearing in February 2020 before allowing work to resume.

Then

The plant opened in 2022, but only after repeated legal interventions and a long permit process.

Now

It established that building ahead of final approval is legal in Germany yet leaves a project exposed to court orders and protests.

Why this matters now

Google's position at Farciennes is similar: a valid older permit, construction pushed ahead on newer plans, and a court deciding whether the newer plans survive.

Sources