Three states approve SWEPCO's gas plant on a retired coal site

Three states approve SWEPCO's gas plant on a retired coal site

Built World

The 450-megawatt Hallsville plant is the first half of a single filing that also converts two Welsh coal units to gas

Overview

Updated 17 minutes ago

A 450-megawatt gas plant on the site of a demolished East Texas coal station now has the approval of three state commissions. SWEPCO said regulators in Texas, Arkansas and Louisiana each finished their review of the Hallsville plant and found it in the public interest, an announcement the company made on Nov. 19.

The approvals cover a single application SWEPCO filed in December 2024, which bundled Hallsville with the conversion of two coal units at its Welsh plant in Texas. Because no commission said no, a fallback plan to shift costs toward the states that did approve stays unused. The orders do not settle final costs or how much of them customers will pay; those questions move to future rate cases.

Why it matters

Ratepayers in three states will pay for a gas plant on a demolished coal site, built to reach full power in 11 minutes.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

450 MW
Plant capacity
Two turbines and two generators of 225 megawatts each, enough for about 400,000 homes at peak, SWEPCO says.
$723M
Combined capital estimate
AEP's estimate for Hallsville plus the Welsh conversion together; it has not published a Hallsville-only figure.
$991/kW
Projected Hallsville cost per kilowatt
The Arkansas order compares it with a $1,216/kW benchmark the commission accepted for Entergy Arkansas' Lake Catherine Unit 5 in April 2025.
250
Jobs SWEPCO attributes to the project
The company says the plant will bring 250 jobs to Hallsville.
11 min
Startup time from a dead start
SWEPCO's stated ramp time to full output, which it markets as emergency capacity for East Texas.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

2024 November 2026

5 events Latest: 2 days ago
Tap a bar to jump to that date
  1. Three commissions clear the Hallsville gas plant

    Latest Regulatory

    Texas, Arkansas and Louisiana regulators have each found the 450-megawatt project in the public interest and finished their review.

  2. Officials tour the Hallsville Energy Hub

    Event

    Community leaders, elected officials and economic development partners get construction updates at the former Pirkey site.

  3. Arkansas enacts a cost-recovery route for new generation

    Legislation

    Act 373, the Generating Arkansas Jobs Act, lets the commission approve recovery through a strategic investment rider.

  4. SWEPCO files one application with three commissions

    Filing

    The company asks Texas, Arkansas and Louisiana regulators to approve the Hallsville plant and convert Welsh Units 1 and 3 to gas.

  5. Pirkey coal plant demolished

    Infrastructure

    The retired coal plant on the Hallsville site is torn down, clearing ground SWEPCO later reuses.

Scenarios

1

Hallsville starts serving customers in late 2027

Likely Resolves by Jan 31, 2028

Discussed by: SWEPCO and AEP filings

With all three commissions finished, construction is the remaining step. SWEPCO targets service in late 2027, and AEP's annual report places in-service dates for the two projects between December 2027 and May 2028. A gas turbine build is shorter than most large generation projects, which is why the schedule is plausible rather than optimistic.

2

Final Hallsville costs land above the $991 per kilowatt estimate

Possible Resolves by End of 2028

Discussed by: Arkansas commission staff and SWEPCO witnesses in Docket 24-052-U

The Arkansas order approved the initial cost estimates as reasonable but said nothing about prudence of final costs. Staff witness Bower raised cost uncertainty as the reason to doubt Hallsville. SWEPCO countered that reordering the same equipment today would cost more, which implies the risk runs one way.

3

Arkansas regulators disallow part of the Hallsville cost

Unlikely Resolves by Q2 2029

Discussed by: Arkansas Public Service Commission staff and the administrative law judge's order

Cost recovery runs through a separate future proceeding, and Arkansas law lets the commission test prudence there. The order that approved construction explicitly reserved that question. A disallowance would not stop the plant; it would shift cost from Arkansas customers to shareholders or to the other two states.

Historical Context

3 moments from history that rhyme with this story — and how they unfolded.

2017–2018

Wind Catcher cancellation (2017–2018)

SWEPCO and parent American Electric Power proposed a large wind farm in the Oklahoma Panhandle and a dedicated transmission line to carry the power to customers in Arkansas and Louisiana. The project needed sign-off from regulators in several states, Texas among them.

Then

The Texas Public Utility Commission rejected the project in July 2018. AEP and SWEPCO cancelled it.

Now

The case became the reference for how one state's commission can end a project that customers in several states would pay for.

Why this matters now

This time SWEPCO bundled Hallsville and the Welsh conversion into a single application in all three states and won all three. The Arkansas order still keeps a cost-shifting fallback in case another state had said no.

February 2021

Winter Storm Uri (February 2021)

A sustained cold snap knocked out gas supply and generating plants across Texas and the southern Plains. Grid operators ordered rolling blackouts, and millions of homes and businesses lost power, some for days.

Then

Texas lawmakers required weatherization of generation and gas infrastructure and rewrote emergency rules for the grid.

Now

The storm moved the regional debate toward paying for capacity that can start on short notice, the trait SWEPCO now markets at Hallsville.

Why this matters now

SWEPCO's case rests on speed: two turbines that reach full output from a dead start in about 11 minutes during emergencies or severe weather.

April 2025

Lake Catherine Unit 5 benchmark (April 2025)

Entergy Arkansas asked the Arkansas Public Service Commission to approve a 446-megawatt combustion turbine at a projected cost of $1,216 per kilowatt. The commission found the cost reasonable and the project in the public interest.

Then

The order set a marker for what Arkansas regulators would accept for a new gas turbine.

Now

When SWEPCO filed, its $991 per kilowatt Hallsville estimate came in under that marker, and the administrative law judge cited the comparison when approving the application.

Why this matters now

It is the yardstick Arkansas used for the project all three states have now cleared.