ExxonMobil approves $4 billion Kizomba redevelopment and reports new Block 15 discovery

ExxonMobil approves $4 billion Kizomba redevelopment and reports new Block 15 discovery

Built World

Kizomba A, Kizomba B and the Likembe field get the money; a 21st find lands at Tchihumba West

Overview

Updated 2 hours ago

ExxonMobil and its Block 15 partners approved a $4 billion redevelopment of the Kizomba A and B fields, Angola's petroleum regulator said on 20 November 2026. The same announcement reported hydrocarbons at the Tchihumba West-01ST1 exploration well, the 21st discovery in a block that is already producing.

The money extends the working life of the Kizomba A and B facilities and pays for the Likembe field. It closes out the Block 15 life-extension programme: Kizomba C was approved in 2025, and the production sharing contract now runs to 2037. Angola is counting on commitments like this one to slow the decline of mature offshore fields.

Why it matters

Angola is betting that sweeter contract terms can keep old deepwater fields alive; $4 billion is the first serious test of that bet.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

$4B
Investment covered by the FID
Covers Kizomba A and B redevelopment plus the Likembe field development.
36%
ExxonMobil's working interest
ExxonMobil operates Block 15; Azule Energy holds 42% across two entities.
21
Discoveries in Block 15
Tchihumba West is the second find in the block this year.
65.4 metres
Hydrocarbon-bearing sandstone at Tchihumba West
The regulator described the reservoir's petrophysical properties as good.
1,400 metres
Water depth at the exploration well
The Valaris DS-9 rig drilled the well, about 350 km northwest of Luanda.
2037
End of the Block 15 production sharing agreement
The extended contract is the legal basis for the new spending.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

November 2025 November 2026

3 events Latest: Yesterday
  1. ANPG announces the $4 billion FID for Kizomba A, B and Likembe

    Latest Investment decision

    Partners formalized the decision the day before; it completes the Block 15 life-extension FIDs begun with Kizomba C.

  2. Tchihumba West-01ST1 finds 65 metres of hydrocarbon-bearing sand

    Discovery

    The Valaris DS-9 rig drilled the well in about 1,400 metres of water, 350 km northwest of Luanda.

  3. Block 15 partners approve Kizomba C life extension

    Investment decision

    The FID keeps the Mondo and Saxi-Batuque facilities running to 2032, pulled forward from a 2026 target after revised contract terms.

Scenarios

1

Likembe produces its first oil before 2030

Possible Resolves by Q2 2030

Discussed by: ANPG and ExxonMobil have both described Likembe as a subsea tieback under active development, the least complex of the sanctioned projects.

Likembe is a tieback to existing Kizomba infrastructure, which removes the need for a new floating production unit. If subsea contracts are placed on schedule, first production would land in the late 2020s and give the block a new source of barrels as Kizomba A and B decline.

2

Block 15 records a 22nd discovery by the end of 2027

Possible Resolves by End of 2027

Discussed by: ANPG, which has reported two finds in the block in 2026 alone and describes remaining exploration potential in the area.

The block has produced 21 discoveries and still has an active exploration programme tied to its existing hubs. A 22nd find would need another exploration well to come in with hydrocarbons and be formally announced by the regulator.

3

Angola holds crude output near 1.1 million barrels a day through 2030

Uncertain Resolves by Q1 2031

Discussed by: ANPG, which has set the 1.1 million barrel a day objective as the benchmark for whether new investment is working.

This is the test of whether life-extension spending and revised contract terms actually offset natural decline at mature fields. It depends on projects like Kizomba A and B, Kizomba C and Likembe delivering on schedule, and on the country's regulatory overhaul attracting enough new drilling.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

November 2025

Kizomba C life-extension FID (2025)

Block 15 partners approved a decision to keep the Mondo and Saxi-Batuque facilities producing to 2032. The project had originally been pencilled in for a 2026 decision and was brought forward after Addendum No. 2 to the production sharing contract improved the terms.

Then

The project moved into detailed planning, service contracting and mobilization.

Now

It set the template for the Kizomba A and B decision a year later: extend what exists, renegotiate the contract, then sanction.

Why this matters now

The November 2026 FID is the second act of the same plan. Without the 2025 Kizomba C precedent, the $4 billion approval would have been harder to justify.

2025

Block 15 production sharing contract extension to 2037 (2025)

Angola and the Block 15 partners amended the production sharing contract, adding improved fiscal terms and running the agreement out to 2037. ExxonMobil has cited the extension as the basis for continued investment in the block.

Then

The amended terms made life-extension work economically viable on facilities that were originally designed for a shorter producing life.

Now

It tied the operator's planning horizon to Angola's, giving both sides an interest in incremental barrels rather than early decommissioning.

Why this matters now

Brian Unietis named the 2037 extension directly when explaining the $4 billion decision, which makes the contract change the enabling event behind the headline.