Mozambique approves revised Rovuma LNG plan, clearing path to investment decision

Mozambique approves revised Rovuma LNG plan, clearing path to investment decision

Built World

Cabinet raises capacity to 18.6 mtpa and switches to electric processing modules; ExxonMobil targets a final investment decision before the end of 2026.

Overview

Updated 35 minutes ago

Mozambique's Council of Ministers approved a revised development plan for Rovuma LNG, replacing the 15.2 million-tonne-a-year design it signed off in 2019 with an 18.6 mtpa plant built from electric processing modules. The government says the change lowers development costs and emissions at a project ExxonMobil has spent years trying to restart in Cabo Delgado.

Approval is a permitting step, not a construction order. The roughly $30 billion project still needs financing and offtake contracts before ExxonMobil's targeted final investment decision by the end of 2026, and first gas is not expected until the early 2030s.

Why it matters

A final investment decision would put Mozambique among Africa's largest LNG exporters, with revenue tied to a province still fighting an insurgency.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

18.6 mtpa
Approved Rovuma LNG capacity
Up from the 15.2 mtpa design approved in 2019.
$30B
Estimated project cost
Standard Bank estimate for the redesigned onshore plant.
25%
Gas reserved for the domestic market
A share of produced gas set aside for Mozambican use under the approved plan.
$121B
Projected state revenue over 25 years
National Petroleum Institute estimate reported by The Energy Year; a long-horizon forecast tied to future gas prices.
50%
ExxonMobil stake after October asset swap
Eni took a matching 50% of the Area 4 floating LNG units in exchange.
40%
Expected emissions cut versus 2019 design
National Petroleum Institute estimate for the electric-module configuration.
12
Electric processing modules
Each about 1.55 mtpa, built in yards and shipped to the Afungi site near Palma.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

2019 November 2026

7 events Latest: Today
Tap a bar to jump to that date
  1. Cabinet approves amended Rovuma LNG plan

    Today Regulatory

    At its 33rd ordinary session on 17 November, the Council of Ministers approved electric processing modules and capacity of 18.6 mtpa, up from 15.2. The plan reserves 25% of gas for the domestic market.

  2. ReCommon sends SACE a cease-and-desist letter

    Civil society

    The Italian advocacy group urges SACE not to insure the project, citing evictions of 643 families from the industrial park site.

  3. Italy's SACE begins reviewing insurance cover

    Finance

    The export credit agency starts assessing cover for the liquefaction plant, storage and marine terminal.

  4. ExxonMobil and Eni swap Area 4 assets

    Corporate

    ExxonMobil's Rovuma stake rises to 50%; Eni takes 50% of the Coral Sul and Coral Norte floating LNG units.

  5. TotalEnergies-led Mozambique LNG resumes construction

    Project

    The $20 billion, 13.1 mtpa project next to Rovuma's site restarts work after a multi-year pause.

  6. Force majeure lifted on Rovuma LNG

    Project

    The operator tells partners it is progressing toward a final investment decision in 2026.

  7. Mozambique approves the original Rovuma design

    Regulatory

    The government signs off on a 15.2 mtpa onshore plant. Insurgent attacks in Cabo Delgado later force operators to evacuate staff and suspend work for years.

Scenarios

1

ExxonMobil announces Rovuma LNG final investment decision before end of 2026

Possible Resolves by End of 2026

Discussed by: ExxonMobil guidance, restated by company executives after the cabinet approval

The company has said repeatedly that it expects a final investment decision before the end of 2026, and the cabinet approval removes the main permitting obstacle. Reaching it requires locked-in financing, offtake contracts and insurance cover from export credit agencies, with SACE still reviewing a transaction it opened in October.

2

Rovuma LNG final investment decision slips into 2027

Possible Resolves by Q2 2027

Discussed by: Analysts covering the project's financing timeline, including dBA's October 2026 supplier note

A $30 billion project in a province still recovering from insurgency needs lenders and insurers comfortable with security risk. If offtake and cover are not in place by December, the decision moves into 2027 and the early-2030s first-gas target drifts. No construction contract would be signed until the decision is taken.

3

SACE approves export credit cover for Rovuma LNG

Uncertain Resolves by Q2 2027

Discussed by: ReCommon, which is campaigning against the cover, and the project's lenders

SACE has been assessing insurance for the liquefaction plant, storage and marine terminal since 16 October 2026. Approval would unlock a share of the financing package; refusal would force the partners to find other backers or absorb more risk themselves. The agency has published no decision either way.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

2019

Rovuma LNG's first development plan (2019)

Mozambique approved a 15.2 mtpa onshore design for gas from Area 4 of the Rovuma Basin, with ExxonMobil, Eni and partners including China National Petroleum Corporation, Mitsui, Galp, KOGAS and ENH. An Islamic State-linked insurgency in Cabo Delgado then forced operators to evacuate staff and suspend work for years.

Then

Construction plans stalled while the security situation deteriorated and hundreds of thousands of people were displaced.

Now

The 2019 design was shelved and replaced. In November 2026 the government approved an 18.6 mtpa version using electric processing modules.

Why this matters now

The plan just approved is a rewrite of the one from 2019, and the seven-year gap explains why cost reduction and security, not geology, set the timetable.

2026

Mozambique LNG's multi-year stoppage and restart

TotalEnergies leads a $20 billion, 13.1 mtpa LNG project adjacent to Rovuma's Afungi site. Insurgent attacks forced a multi-year pause on work, putting the two schemes that together represent roughly $50 billion of liquefaction capacity in the same stalled position.

Then

Construction formally resumed in 2026, restoring activity in a province still working through the aftermath of violence.

Now

Resettlement of families from the industrial park area continues, with costs shared by the Area 1 and Area 4 partners.

Why this matters now

It is the closest test of whether large onshore gas construction can proceed in Cabo Delgado, and lenders to Rovuma will read its progress before committing.