PSO breaks ground on 450 MW gas plant after clearing county zoning fight

PSO breaks ground on 450 MW gas plant after clearing county zoning fight

Built World

Two GE turbines at Oologah are due online in December 2028, part of a $1.2 billion PSO generation portfolio.

Overview

Updated 1 hour ago

Public Service Company of Oklahoma began construction on two natural gas turbines at its Northeastern Energy Campus near Oologah, about 30 miles northeast of Tulsa. The units, Northeastern 5 and 6, add 450 megawatts of dispatchable power, with commercial operation targeted for December 2028.

Reaching the groundbreaking took a year of litigation. Rogers County's Board of Adjustment denied PSO a zoning exception in November 2025, PSO sued, and a judge granted the utility a land-use exemption in June 2026. State regulators had already approved the spending in May, with conditions meant to keep household bills insulated from data-center demand.

Why it matters

The 450 megawatts are meant to meet Oklahoma demand forecast to grow 146% by 2036, and customers start paying before the power flows.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

450 MW
Capacity of Northeastern Units 5 and 6
Two GE gas turbines in simple-cycle configuration.
$539.8M
Estimated capital cost of the gas units
Figure PSO cited in its Rogers County zoning dispute and CWIP request.
$1.2B
OCC-approved generation portfolio
Covers two gas units, three battery storage systems and power purchase agreements.
146%
Forecast load growth by 2036
PSO's 2026 planning refresh projects 6,456 MW of added load versus its 2024 forecast.
December 2028
Target commercial operation date
PSO's stated in-service date for both new turbines.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

October 2024 November 2026

8 events Latest: Today
Tap a bar to jump to that date
  1. PSO breaks ground on Northeastern Units 5 and 6

    Today Construction

    PSO announced the start of construction on Nov. 9; the 450 MW project is due online in December 2028.

  2. OCC approves $1.2 billion portfolio and CWIP

    Regulation

    Commissioners vote 2-1 to preapprove the projects and allow billing during construction.

  3. PSO announces two gas turbines for Oologah

    Announcement

    The utility discloses plans to add 450 megawatts at its existing Northeastern campus.

  4. PSO issues its baseline resource plan

    Planning

    The 2024 integrated resource plan sets the forecast that the 2026 refresh later revises sharply upward.

Scenarios

1

Both Oologah turbines enter service in December 2028

Likely Resolves by Jan 31, 2029

Discussed by: PSO project filings and local reporting on the construction schedule

PSO has given a December 2028 commercial operation date since it announced the project, and the zoning ruling removed the main permitting obstacle. If construction proceeds on that schedule, the units would be available for the summer 2029 peak and the winter after it.

2

Construction slips past 2028 and the cost estimate rises

Possible Resolves by End of 2029

Discussed by: Oklahoma Energy Today, which has tracked the project's cost and legal history

Gas turbine supply chains and interconnection work have stretched schedules for other utilities. A slip would push the 450 megawatts past the 2029 peak and reopen the question of whether the $539.8 million estimate holds, especially with CWIP billing already tied to the project.

3

A court challenge halts CWIP cost recovery

Uncertain Resolves by End of 2027

Discussed by: Oklahoma Energy Today, which reported in May 2026 that a constitutional challenge to the financing method was expected

Construction-work-in-progress lets PSO bill customers for the gas units before they generate power. A successful constitutional challenge would cut off that cash flow mid-build and force PSO to carry the cost until the units enter service, changing who bears the financing risk.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

February 2021

Winter Storm Uri (2021)

A prolonged cold snap pushed the Southwest Power Pool into controlled outages, and millions of homes and businesses across Texas and the Southern Plains lost power. Gas supply and generating equipment failed in conditions the regional grid had not planned for.

Then

Grid operators ordered rolling blackouts across the SPP footprint, and Oklahoma utilities faced scrutiny over fuel security.

Now

Utilities and regulators put more weight on dispatchable, on-site generation and weatherized fuel supply when planning new capacity.

Why this matters now

PSO cites reliability during extreme spring and winter weather as a main reason for adding gas turbines at an existing site rather than relying on wind and storage alone.

May 2026

Oklahoma's House Bill 2992 (2026)

Oklahoma lawmakers passed legislation directing the Corporation Commission to protect household rates as large loads such as data centers connect to the grid. Governor Kevin Stitt signed it the same week the commission voted on PSO's portfolio.

Then

The commission attached conditions to its PSO approval, including annual rate adjustments as new demand arrives and separate terms for data-center connections.

Now

Cost allocation between households and large industrial customers became an explicit part of every new generation approval in the state.

Why this matters now

The Oologah build is one of the first projects approved under the new cost-allocation rules, so who pays for the 450 megawatts is now a regulatory question, not just a construction one.