Third Street Bridge rehabilitation (2017–2020)
San Francisco Public Works repaired corrosion on the Lefty O'Doul Bridge, replacing steel members, concrete counterweights, support piles and the bridge deck. Crews worked from barges and with underwater divers. The bridge was locked in the down position for the second phase, closing it to maritime traffic.
The bridge stayed open to pedestrians, cyclists and vehicles through most of the work and fully reopened in May 2020.
Drawbridge lifts resumed May 1, 2020, restoring maritime access to Mission Creek.
It shows how long corridor-scale work on Third Street runs, and that the street's closures have ended before.