PG&E service delays hit San Francisco small businesses

PG&E service delays hit San Francisco small businesses

Built World San Francisco, CA local

A bakery opening is pushed to February after PG&E cuts power over unpermitted wiring

Overview

Updated 1 hour ago

Lorella, a bakery from award-winning chef Melissa Perello and pastry chef Melissa Loar, was supposed to open on Polk Street before the holidays. On Halloween, PG&E cut power to the building after an inspection found unpermitted wiring, pushing the opening to February at the earliest.

The delay is one of four businesses in the same building left without power. It comes as PG&E warns 25,000 prospective customers of potential six-month delays in getting electricity, and as San Francisco officials cite such delays in their bid to take over the utility's grid.

Why it matters

If PG&E's service delays persist, small businesses across San Francisco face months of lost revenue and construction costs, while the city's takeover bid gains political momentum.

Last Monday's email for San Francisco, CA

Sent Nov 16. It carried:

Get next Monday's: one short email a week. Free. Unsubscribe in one click.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

3 months
Delay for Lorella opening
Originally slated for the holidays, now expected in February.
4
Businesses in building without power
Lorella, Bageletto, Street Restaurant, and X'Core Pilates.
25,000
PG&E customers warned of connection delays
Utility warns of potential six-month delays amid $2B spending postponement.
$2B
PG&E postponed spending
Utility postpones $2 billion in planned spending amid wildfire liability uncertainty.
12 weeks
Minimum expected upgrade time
PG&E says the full panel upgrade will take at least 12 weeks.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

October 2026 November 2026

5 events Latest: Yesterday
Tap a bar to jump to that date
  1. Lorella opening delayed to February

    Latest Business

    The San Francisco Standard reports Lorella's opening pushed to February after PG&E mandates full panel upgrade.

  2. PG&E says working on temporary solution

    Statement

    PG&E spokesperson Fiona Chan says utility is committed to working with customer on upgraded service and temporary power.

  3. Bageletto co-owner says delay throws wrench in financials

    Business

    Kiki Theodorides says delay is 'throwing a wrench in the financials' for family-owned bagel shop.

  4. Street Restaurant serving drinks by candlelight

    Business

    Street Restaurant has been serving martinis by candlelight without a functioning kitchen for over two weeks.

  5. PG&E cuts power to Polk Street building

    Utility

    PG&E cuts power to 2139 Polk St. after inspection finds unpermitted three-phase wiring.

Scenarios

1

Lorella Opens in February 2027 After PG&E Upgrade

Likely Resolves by Mar 1, 2027

Discussed by: The San Francisco Standard, Gazetteer SF

PG&E completes the mandated panel upgrade and restores power, allowing Lorella to finish construction and open in February. The bakery's team uses a commissary kitchen in the meantime to keep staff employed and start wholesale sales.

2

PG&E Delays Extend Past Spring, Forcing Business Closures

Possible Resolves by Jun 1, 2027

Discussed by: Melissa Perello, Kiki Theodorides

The electrical upgrade takes longer than the 12-week estimate, stretching into summer 2027. Street Restaurant and Bageletto, already losing revenue, decide they cannot wait and close permanently. Lorella survives but delays further.

3

San Francisco Advances Municipal Takeover of PG&E Grid

Unlikely Resolves by Jan 1, 2028

Discussed by: NBC Bay Area, San Francisco city officials

Citing service delays like the Polk Street outage, San Francisco officials push forward with their bid to take over PG&E's local grid. The California Public Utilities Commission opens proceedings to determine the purchase price.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

November 2018 - January 2019

Camp Fire and PG&E Bankruptcy (2018-2019)

PG&E's equipment sparked the Camp Fire, which killed 85 people and destroyed the town of Paradise. Facing more than $30 billion in liabilities, the utility filed for Chapter 11 bankruptcy in January 2019.

Then

PG&E emerged from bankruptcy in 2020 but remained under financial pressure.

Now

The utility has raised rates and deferred spending, citing wildfire liability uncertainty.

Why this matters now

PG&E says wildfire liability uncertainty is why it is postponing $2 billion in spending, which is causing service connection delays like the one affecting Lorella.

September 2010

San Bruno Pipeline Explosion (2010)

A PG&E natural gas pipeline exploded in San Bruno, killing eight people and destroying 38 homes. Investigators found the utility had failed to maintain the pipeline properly.

Then

PG&E was fined $1.6 billion and ordered to reform its safety practices.

Now

The disaster cemented PG&E's reputation for infrastructure failures and regulatory scrutiny.

Why this matters now

It shows PG&E's long history of maintenance and safety issues, which shapes how customers and regulators view the current electrical delays.