San Francisco Housing Policy and Practice Review (2023)
The governor's office published a review of why San Francisco builds housing so slowly. It found the city averaged 523 days to grant a developer entitlements, the slowest in California; the next slowest city averaged 385. After entitlements, a developer waited an average of another 605 days for a building permit.
The review gave state officials a documented case that city procedures, not just market conditions, were holding back construction.
Processing time became the measure against which the city's housing promises are checked, and the 22,000-permit gap is the latest number on that ledger.
The shortfall behind the January 2027 deadline has the same root the review identified: a permitting pipeline that moves slower than the state's targets assume.