Adani Carmichael coal mine approvals (2014-2019)
The federal environment minister approved the Carmichael coal mine in 2014. The Federal Court set that approval aside in 2015 over conservation advice for two threatened species, and the approval was reissued in 2016. State conditions, legal challenges and financing fights continued for years after.
Approval was overturned and reissued, adding years before construction could proceed.
The case became the reference point for how long contested environmental approvals can take in Australia.
It is the contrast case for the two-month federal review of the Western Downs data centre: one project absorbed years of process, the other was waved through.