Egypt's 900 MW Shokeir wind farm reaches financial close

Egypt's 900 MW Shokeir wind farm reaches financial close

Built World

ENGIE, Aeolus and Orascom secured about $588 million in non-recourse debt for Gulf of Suez Wind Farm 3.

Overview

Updated 2 hours ago

The 900-megawatt Shokeir wind farm has reached financial close, the point at which lenders release the debt a project needs to build at full scale. The project company is owned by Aeolus (40%), ENGIE (35%) and Orascom Construction (25%).

Six lenders are providing about $588 million in non-recourse debt, meaning they are repaid from the project's revenue rather than the owners' balance sheets. The farm's 86 Goldwind turbines are expected to generate about 4 terawatt-hours a year once fully running in 2028.

Why it matters

The farm could supply about 4 TWh a year, enough for 1.4 million Egyptian households, and help Egypt hit 45% renewables by 2028.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

900 MW
Wind farm capacity
Onshore wind project in the Gulf of Suez.
$588 million
Non-recourse project debt
Syndicated loan from six lenders.
86
Goldwind turbines
Each turbine is rated at 10.5 MW.
4 TWh
Expected annual output
About 1.4 million Egyptian households' consumption.
2 million tonnes
Annual CO2 avoided
Expected reduction once fully operational.
1.8 GW
Consortium's Egyptian wind capacity
Combined capacity after Shokeir joins two existing farms.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

Organizations Involved

Timeline

March 2026 November 2026

5 events Latest: 2 days ago
Tap a bar to jump to that date
  1. Financial close reported

    Latest Announcement

    Construction Review reports the close and project details.

  2. Financial close reached

    Finance

    Six lenders commit about $588 million in non-recourse debt.

  3. Cabinet grants golden license

    Permit

    License sets a completion deadline of November 1, 2028.

  4. Construction begins

    Construction

    Work starts on the 900 MW wind farm before financial close.

  5. Power purchase agreement signed

    Contract

    Sponsors sign a 25-year power purchase agreement with EETC.

Scenarios

1

First 300 MW enters commissioning in January 2028

Likely Resolves by Feb 28, 2028

Discussed by: Shokeir Wind Energy and ENGIE project statements

The sponsors plan to connect the wind farm in three phases. The first 300 MW is expected to begin commissioning in January 2028.

2

Full 900 MW reaches commercial operation by September 2028

Possible Resolves by Oct 31, 2028

Discussed by: ENGIE and Toyota Tsusho project statements

The sponsors target full commercial operation in the third quarter of 2028. The project would then generate about 4 TWh a year.

3

Construction slips past the November 2028 golden-license deadline

Unlikely Resolves by Nov 1, 2028

Discussed by: EnterpriseAM and project documents

The Cabinet's golden license points to completion on November 1, 2028. That gives the project room beyond its September 2028 target.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

2017-2019

Gulf of Suez Wind Farm I (2019)

Toyota Tsusho group invested in Egypt's first wind power independent power producer project in 2017. The 262.5 MW plant reached commercial operation in October 2019.

Then

The project showed that Egypt could attract private wind developers under long-term power purchase agreements.

Now

It became the first phase of a three-project wind portfolio in the Gulf of Suez.

Why this matters now

Shokeir is the third project in that same portfolio and uses the same build-own-operate model.

2023-2025

Gulf of Suez Wind Farm II (2025)

The same consortium built a roughly 650 MW wind farm in the Gulf of Suez. Construction began in 2023 and commercial operation started in June 2025.

Then

The project added substantial wind capacity to Egypt's grid and was delivered ahead of schedule.

Now

It gave ENGIE, Aeolus and Orascom a working template for larger projects.

Why this matters now

Shokeir is bigger than both earlier farms combined and will take the consortium's Egyptian wind capacity to about 1.8 GW.