France grants Geothermar a geothermal exploration permit near Marseille

France grants Geothermar a geothermal exploration permit near Marseille

Built World

A five-year, 390-square-kilometre licence to hunt for hot water under the Bouches-du-Rhône, with Vitrolles and its airport as the first customer

Overview

Updated 52 minutes ago

Geothermar SAS now holds a five-year exclusive right to explore for deep geothermal heat beneath 390 square kilometres of the Bouches-du-Rhône, covering Marseille and 22 other communes. The permit was signed on 4 October 2026 and obliges the company to spend at least €16.54 million on exploration.

The first project is a 15-megawatt heating plant near Marseille Provence airport, feeding about 20 kilometres of pipe through Vitrolles by 2030-2031. Surveys have mapped aquifers at 1,400 to 2,600 metres, with water temperatures estimated at 60 to 90°C.

Why it matters

If the wells deliver, heating for Vitrolles homes, the Marseille airport and Airbus Helicopters could come from underground water instead of gas.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

390 km²
Permit area
Exclusive exploration rights across 23 communes in the Bouches-du-Rhône.
€16.54M
Minimum exploration commitment
Sum Geothermar pledged to spend on research during the five-year permit.
23
Communes covered
From Marseille and Marignane to Aix-en-Provence and Gardanne.
15 MW
Planned Vitrolles plant capacity
First facility, targeted for commissioning in 2030-2031.
53 MW
Estimated resource potential
Developer estimate for a fuller build-out, alongside 81 GWh of heat a year.
15,000 t
Estimated CO₂ avoided per year
Developer figure based on Cerema and ADEME data for the first project.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

2013 November 2026

7 events Latest: Today
Tap a bar to jump to that date
  1. Permit terms reported internationally

    Today Disclosure

    Coverage confirms the five-year term, 23 communes, €16.54 million commitment and Vitrolles plant.

  2. Project unveiled at mayors' trade fair

    Announcement

    Geothermar presents the Vitrolles plant and network plan at the Salon des Maires.

  3. Minister signs the permit

    Regulatory

    An arrêté grants Geothermar five years of exclusive exploration across 390 square kilometres.

  4. NGE buys 49% of Gaia

    Ownership

    The infrastructure group deepens its hold on the developer behind Geothermar.

  5. Public consultation and resource survey

    Consultation

    Public comment opens; ADEME and BRGM report on the area's deep geothermal potential.

  6. Permit application filed

    Filing

    Geothermar asks for exclusive exploration rights over the Marseille-Berre area for five years.

  7. Geothermar is founded

    Formation

    NGE and Gaia Energy Systems create a joint venture to develop geothermal heat projects.

Scenarios

1

Exploration wells find a usable reservoir

Possible Resolves by Oct 4, 2031

Discussed by: Geothermar and NGE project statements; the government's IGEDD review of the permit application

The five-year permit exists to answer one question: whether the aquifers at 1,400 to 2,600 metres flow fast enough and hot enough to supply a heat network. Geothermar has said it plans one or two exploratory well pairs. A successful test opens the way to the Vitrolles plant; a poor one sends the company back to modelling with the clock running.

2

Vitrolles plant enters service by 2031

Uncertain Resolves by Q2 2032

Discussed by: Geothermar, NGE and the mayor of Vitrolles

The 15-megawatt plant near Marseille Provence airport and the 20-kilometre network are the project's measurable output. Delays would most likely come from drilling results, drilling permits or the heat network concession with the city, not from the exploration licence itself.

3

Permit expires without a well drilled

Unlikely Resolves by Oct 4, 2031

Discussed by: IGEDD, the government review body that noted earlier Geothermar permits produced no works

France's review of the application flagged that previous permits held by Geothermar did not lead to the drilling originally promised, and criticised the application's environmental impact analysis as incomplete. A permit can run out quietly if financing, drilling authorisations or local approval stall.

Historical Context

3 moments from history that rhyme with this story — and how they unfolded.

1970s-present

Paris Basin Dogger geothermal heating (1970s onward)

After the 1973 oil shock, French drillers went into the Dogger limestone beneath the Paris region, tapping water at roughly 1,500 to 2,000 metres and building dozens of district heating networks. When oil prices fell in the 1980s, many of those networks were shut down; others were refurbished from the 1990s and still run today.

Then

A wave of networks opened, then a wave closed as gas and oil got cheap again.

Now

The surviving systems made the Paris region one of the largest users of geothermal district heating in Europe.

Why this matters now

It shows the geology under a French sedimentary basin can heat whole districts. The economics, not the rock, decided which networks lasted.

1987-2016

Soultz-sous-Forêts deep geothermal pilot (1980s-2010s)

In Alsace, French and German researchers drilled deep into granite to test whether engineered fractures could extract heat from hot dry rock. The site produced scientific results and a small generating plant, but never became a commercial power station.

Then

The project confirmed that deep drilling in France is technically feasible.

Now

It left deep geothermal in France associated with research budgets rather than bankable heat sales.

Why this matters now

Geothermar is taking the opposite route: sedimentary aquifers and a heat network with named customers, not electricity from engineered rock.

1940s-present

Reykjavik's shift to geothermal district heating (1940s onward)

Iceland's capital moved its space heating from coal to hot water piped from geothermal fields, starting with the first municipal network in the 1940s and expanding as drilling improved. Today geothermal heat supplies the large majority of Icelandic homes.

Then

Households cut coal use and smoke levels fell in the city.

Now

District heating became the default way Icelandic towns are warmed, insulated from imported fuel prices.

Why this matters now

It is the clearest example of what an anchor heat network does once the resource is proven: it replaces a fuel supply chain with local pipes.