Court upholds refusal to restart Redbank as a biomass plant

Court upholds refusal to restart Redbank as a biomass plant

Rule Changes

Verdant Earth's conversion plan has now failed at the local council, the state planning commission and twice in court

Overview

Updated Yesterday

For six years, a mothballed coal plant in the NSW Hunter Valley has been trying to reopen as a biomass generator, burning invasive native scrub cleared from farmland in the state's west. On November 26, the NSW Land and Environment Court dismissed the owner's appeal against the planning refusal that stopped it.

The case turned on fuel, not turbines. NSW rules let generators burn plant material, and Verdant Earth Technologies' plan relied on invasive native species cleared from farmland under a government-approved program. The Independent Planning Commission refused the project in September 2025, finding it could not accept, without thorough assessment, that the extra clearing would have no flow-on environmental effects.

Why it matters

NSW still lets native vegetation cleared from farmland be burned for electricity. This ruling blocks one plant, not the rule.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

700,000
Biomass fuel sought per year
Dry tonnes the plant proposed to burn annually, from invasive native species and purpose-grown crops.
151 MW
Generation capacity
The same capacity the station had as a coal plant.
200,000
Homes the developer said it could power
Verdant's figure for the plant's contribution to the grid.
6,635 ha
Invasive native species cleared per year, average
Actual clearing averaged against 100,000 hectares certified annually, the commission found.
95%
Submissions opposing the project
Nearly 600 submissions went to the planning commission before its refusal.
A$800M
Developer's estimate of the plant's value
Verdant's figure, far above the $70 million capital cost cited in its original application.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

1993 November 2026

11 events Latest: Yesterday Showing 8 of 11
Tap a bar to jump to that date
  1. Planning commission refuses the project

    Decision

    After nearly 600 submissions, the Independent Planning Commission found the fuel strategy's environmental impacts unaddressed.

  2. Verdant files a state-significant application

    Filing

    The company sought fresh consent for up to 700,000 dry tonnes of biomass a year.

  3. Singleton Council rejects biomass conversion

    Decision

    The council refused Verdant's modification application after strong local opposition.

  4. Verdant Earth buys the dormant station

    Acquisition

    The company took over the site intending to turn it into a bioenergy hub.

  5. Plant shuts after losing cheap coal

    Closure

    Redbank entered care and maintenance when its supply of coal tailings ran out.

  6. Redbank commissioned as a 151 MW coal plant

    Infrastructure

    The station began operating on coal tailings from the Warkworth mine.

  7. Redbank approved as a coal-waste plant

    Approval

    The original consent allowed a power station burning coal mining waste, known as fines.

Scenarios

1

Redbank site reopens as a data centre or battery

Possible Resolves by End of 2027

Discussed by: Verdant Earth chief executive Richard Poole, speaking to the ABC after the ruling

Poole said the company would regroup and that the site could become 'a data centre, maybe it's a battery site'. Voltic DC had already explored an AI training campus of up to 500 megawatts on adjoining land under a shared-infrastructure agreement. Any pivot needs a fresh development application to the state, and the existing grid connection is the main asset either way.

2

Verdant appeals the ruling on a question of law

Unlikely Resolves by Q2 2027

Discussed by: Poole said he would meet his legal team to examine next steps

A merit appeal decides the facts, so the only route left is the NSW Court of Appeal on a claimed error of law. That is a narrower argument than the case just lost, and no appeal had been filed when the ruling was handed down.

3

NSW closes the biomass land-clearing rules before the election

Possible Resolves by Q2 2027

Discussed by: Nature Conservation Council of NSW and Greens NSW, both calling for rule changes after the ruling

Both groups said the decision blocks one project without changing the eligibility rules that let cleared native vegetation count as fuel. The conservation council wants the invasive native species classification scrapped and says it will campaign on it before the state election due in March; the Greens want the environment operations regulation amended.

4

Another biomass developer tests the same fuel route

Uncertain Resolves by End of 2027

Discussed by: No developer has announced one; the possibility follows from the rules left unchanged

The court ruling decides this application, not the eligibility of native vegetation as fuel. A different proponent could still propose a generator on the same fuel strategy, and would face the same question the commission raised here: whether the clearing it depends on has been properly assessed.

Historical Context

3 moments from history that rhyme with this story — and how they unfolded.

1994

Greenpeace's challenge to Redbank's coal approval (1994)

Greenpeace went to court to overturn the 1993 consent for a coal-waste power station at Redbank. It is described as Australia's first climate litigation. The court dismissed the application.

Then

The plant was built and commissioned in 2001 as a 151 megawatt coal generator.

Now

The site has returned to court repeatedly, with each case narrowing what can be done under the original consent.

Why this matters now

The November 26 ruling is the third court case over the same piece of land.

2022

The fuel-switch ruling (2022)

Verdant appealed Singleton Council's 2021 refusal of its modification application. The Land and Environment Court dismissed the appeal, ruling that changing the fuel from coal to biomass was not 'substantially the same' development as the original approval.

Then

Verdant had to start over with a full state-significant development application, filed in 2024.

Now

The decision put the project's fuel supply chain at the centre of every later assessment.

Why this matters now

That full application is the one the planning commission refused and the court upheld.

2014

Redbank's first closure (2014)

The station shut and went into care and maintenance after losing its supply of cheap coal tailings from the Warkworth mine. The turbines and grid connection stayed in place.

Then

The site sat idle for four years before Verdant bought it.

Now

The ready-made grid connection is what made repeated conversion attempts worth the legal cost.

Why this matters now

Both of Redbank's operating lives ended over fuel supply rather than equipment.