SPP picks Longview to build New Mexico line for oilfield power demand

SPP picks Longview to build New Mexico line for oilfield power demand

Built World

A 50-mile, 115-kilovolt line across Lea and Eddy counties is one piece of a $23.7 billion regional transmission plan

Overview

Updated Yesterday

Oilfield operators in southeastern New Mexico are swapping diesel equipment for electric motors, and the power has to come from somewhere. On Nov. 17, the Southwest Power Pool picked Longview Infrastructure Southwest to build a 50-mile, 115-kilovolt line linking four substations in Lea and Eddy counties. Target in-service date: June 2029.

The line is the small, local end of something larger. SPP's board approved a $23.7 billion transmission portfolio the same day, sized for peak demand rising from about 58 gigawatts in 2026 to as much as 110 gigawatts by 2035. SPP's 2025 plan attributes roughly 4,000 megawatts of new firm load on the local system mainly to oil and gas electrification.

Why it matters

Permian oilfield electrification is adding gigawatts to a grid where new projects can wait four years for a connection.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

4,000 MW
New firm load in SPP's 2025 plan
Mostly oil and gas operators moving equipment off diesel.
$23.7B
Cost of projects in SPP's 2026 transmission portfolio
SPP projects $2.27 to $6.38 in benefits per dollar invested.
4.2 to 17 GW
Permian Basin electricity use, projected to 2032
A New Mexico state report expects roughly a fourfold increase.
58 to 110 GW
SPP peak demand, 2026 to 2035
Upper bound of SPP's 2035 forecast range.
50 miles
Length of the Phantom–Battle Axe–Ponderosa–Dollarhide line
Connects four substations across two counties.
$595M
PNM's planned New Mexico transmission project
The utility expects to file for state approval.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

2025 November 2026

6 events Latest: 4 days ago
Tap a bar to jump to that date
  1. Line details disclosed: 115 kV, four substations, 50 miles

    Latest Disclosure

    The route links the Phantom, Battle Axe, Ponderosa and Dollarhide substations.

  2. Longview confirms award and June 2029 target

    Statement

    The developer says it will begin permitting and right-of-way work across two counties.

  3. SPP board approves record $23.7B transmission portfolio

    Decision

    The 2026 plan includes a 765-kilovolt backbone and authorizes notices to construct.

  4. SPP selects Longview for Lea and Eddy counties line

    Selection

    A five-member expert panel unanimously recommended Longview over two competing proposals.

  5. State report projects Permian power use will quadruple

    Report

    New Mexico analysts forecast Permian electricity use rising from 4.2 to more than 17 gigawatts by 2032.

  6. SPP plan flags 4,000 MW of new oilfield load

    Planning

    The 2025 Integrated Transmission Plan identifies firm load expected on the local utility system.

Scenarios

1

Line enters service in June 2029 as scheduled

Likely Resolves by Q2 2029

Discussed by: Longview Infrastructure and SPP project schedules

Longview clears permitting and right-of-way in Lea and Eddy counties, builds the 50-mile line and energizes it on its stated target. This is the baseline the company and SPP are planning around; slippage of a year or more is common for projects of this size.

2

Permian load outruns the plan and SPP adds more capacity

Possible Resolves by End of 2028

Discussed by: SPP planning documents and New Mexico state reports

If oilfield electrification and data-center demand arrive faster than forecast, the 4,000 megawatts identified in 2025 will look small. SPP would then need a second wave of projects in Lea and Eddy counties, and the question becomes whether those lines can be permitted before operators give up and keep burning diesel.

3

New Mexico regulators push back on who pays

Uncertain Resolves by Q2 2028

Discussed by: New Mexico Energy Affordability and Grid Reliability Council

The council's report warns that infrastructure built for large industrial load can shift costs onto households, rural customers and tribes. If the Public Regulation Commission attaches conditions to transmission certificates or rejects a cost allocation, projects like PNM's planned $595 million filing could be delayed or reworked.

Historical Context

3 moments from history that rhyme with this story — and how they unfolded.

July 2011

FERC Order 1000 (2011)

The Federal Energy Regulatory Commission required regional grid operators to plan transmission across their footprints and to solicit competing proposals for new lines, rather than handing projects automatically to the incumbent utility.

Then

Utilities litigated and compliance dragged on for years.

Now

Competitive selection became routine, and developers that own no wires could win projects.

Why this matters now

Longview's win over two competing proposals runs through the process Order 1000 created.

2005–2014

Texas competitive renewable energy zones (2005–2014)

Texas regulators designated zones in West Texas for wind development and approved a transmission buildout to carry the power east, with costs spread across the state's ratepayers.

Then

Construction took most of a decade and the cost allocation drew complaints from customers far from the turbines.

Now

West Texas wind capacity grew sharply, and the model became a reference for planners building lines ahead of demand.

Why this matters now

It is the closest precedent for building transmission in anticipation of Permian load rather than waiting for it to arrive.

2019

New Mexico Energy Transition Act (2019)

New Mexico set a schedule to move its electricity supply to lower-carbon sources, adding large volumes of new generation that also needs transmission capacity.

Then

Utilities began retiring coal plants and procuring replacements.

Now

Transmission planning now has to serve both new industrial load and the state's carbon targets at once.

Why this matters now

It is the second demand on the same wires the Permian buildout is competing for.