Pull to refresh
Logo
Ontario's nuclear fleet renewal

Ontario's nuclear fleet renewal

Built World

Bruce Power's six-unit rebuild is halfway done while OPG starts over at Pickering

Overview

Updated 4 days ago

Ontario is running two nuclear refurbishments at once. Bruce Power returned Unit 3 to the grid in 2026, seven months ahead of its January 2027 target and $150 million under budget, and says it is halfway through a six-unit, $13 billion program. Ontario Power Generation finished Darlington's four units in February 2026.

At Pickering, Ontario Power Generation took the last of four reactors offline on Sept. 30, 2026, and started site construction on a refurbishment the province calls Canada's largest clean energy project. The units are due back in the mid-2030s at up to 2,200 megawatts. Reactor work waits on a Canadian Nuclear Safety Commission decision expected in January 2027.

Why it matters

Half of Ontario's electricity comes from these reactors, so every year a unit sits idle is power the province must buy elsewhere.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

2 of 6
Bruce Power units returned to service
Unit 6 came back in 2023 and Unit 3 in 2026; Units 4, 5, 7 and 8 are still to be rebuilt
4
Pickering reactors offline
Units 5 to 8 were all shut down by Sept. 30, 2026 for refurbishment
2,200 MW
Pickering capacity after refurbishment
Enough to power about 2.2 million homes, according to the Ontario government
75%
Projected demand increase
Ontario electricity demand forecast to grow 75% by 2050 in the IESO's October 2024 outlook
~50%
Nuclear share of Ontario power
Nuclear energy provides roughly half of Ontario's electricity generation

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

December 2016 October 2026

14 events Latest: October 9th, 2026 · 3 weeks ago Showing 8 of 14
Tap a bar to jump to that date
  1. CNSC Hears Pickering Licence and Refurbishment Case

    Latest Regulatory

    The Canadian Nuclear Safety Commission held a two-part hearing in June and the week of Oct. 6 on OPG's request for a 10-year licence from 2027 to 2036 and approval to refurbish Units 5 to 8. No decision had been published.

  2. Last Pickering Reactor Shut Down for Refurbishment

    Operations

    OPG powered down Unit 6, the last of the station's four B units to come offline, closing a chapter that began in 1971.

  3. Aecon and AtkinsRéalis Tapped for Pickering Overhaul

    Contract

    Engineering News-Record reported the two firms will lead the Pickering refurbishment, a project it tied to Ontario's push to shore up its economy against US tariffs.

  4. Ontario Begins Pickering Refurbishment Construction

    Construction

    The province announced the start of site construction at Pickering, a project it says will extend the four reactors' lives by up to 38 years. The work includes replacing 1,520 fuel channels, 48 boilers and building a 1.5-kilometre deep-water intake.

  5. Bruce Power Unit 3 Construction Phase Complete

    Milestone

    Bruce Power completes the construction phase of the Unit 3 refurbishment on budget and on plan, with the reactor then expected back in service later in 2026.

  6. Darlington Refurbishment Complete

    Milestone

    Ontario Power Generation completes all four Darlington reactor refurbishments ahead of schedule and $150 million under the $12.8 billion budget.

  7. Bruce Power Unit 3 Returns to the Grid

    Operations

    Unit 3 came back seven months ahead of its January 2027 target and $150 million under budget, the Ontario government said. It had been offline since March 2023.

  8. IESO Approves Unit 5 Refurbishment

    Regulatory

    The Independent Electricity System Operator verifies Bruce Power met requirements to proceed with Unit 5 refurbishment, scheduled for late 2025.

  9. Unit 4 Refurbishment Begins

    Construction

    Bruce Power begins Unit 4 Major Component Replacement, the third reactor to enter the refurbishment program.

  10. Unit 6 Returns to Commercial Service

    Operations

    Unit 6 declared commercially operational exactly 39 years after its original in-service date, completing the first full refurbishment cycle.

  11. Unit 6 Construction Phase Complete

    Milestone

    Bruce Power completes the construction phase of Unit 6 refurbishment on time and on budget, including replacement of 480 fuel channels and eight steam generators.

  12. Unit 3 Refurbishment Begins

    Construction

    Bruce Power begins the Major Component Replacement outage for Unit 3, the second reactor in the refurbishment sequence.

  13. Unit 6 Refurbishment Begins

    Construction

    Bruce Power takes Unit 6 offline to begin the first Major Component Replacement, marking the start of the refurbishment program.

  14. Bruce Power Signs $13 Billion Refurbishment Agreement

    Contract

    Bruce Power and the Ontario government sign an amended agreement for the Major Component Replacement program covering Units 3-8, extending site operations to 2064.

Scenarios

1

Bruce Power Completes All Six Refurbishments On Schedule By 2033

Likely

Discussed by: Bruce Power, Ontario Ministry of Energy, Independent Electricity System Operator

The refurbishment program continues its track record of on-time, on-budget delivery through Units 4, 5, 7, and 8. By 2033, all six reactors operate with extended 40-year lifespans, and output increases from 6,400 MW to over 7,000 MW through efficiency upgrades. Bruce Power maintains its position as North America's leading CANDU refurbishment operator, potentially positioning it for international contracts.

2

Cost Overruns and Delays Plague Later Units

Possible

Discussed by: Energy analysts, Canadian Centre for Policy Alternatives, past CANDU refurbishment critics

As the program progresses, supply chain constraints, labor shortages, or technical complications cause schedule slippage and budget increases on Units 5, 7, or 8. This would mirror the experience of New Brunswick's Point Lepreau refurbishment, which ran three years late and $1 billion over budget. Critics argue the early successes may not be replicable as the workforce spreads across multiple concurrent projects.

3

Bruce C Expansion Approved, New Reactors Planned

Possible

Discussed by: Ontario government, Bruce Power, Ontario Chamber of Commerce

Building on refurbishment success, Ontario approves the proposed Bruce C project to construct up to 4,800 MW of new nuclear capacity at the Bruce site. An Ontario Chamber of Commerce analysis projects this would add $217 billion to provincial GDP over the plant's lifespan and create 18,900 construction jobs annually. Construction could begin in the early 2030s as refurbishment wraps up.

4

Demand Growth Outpaces Nuclear Expansion

Uncertain

Discussed by: IESO planning outlooks, clean energy advocates, grid analysts

Even with successful refurbishments, the 75% demand growth forecast proves conservative as data centers, EV adoption, and industrial reshoring accelerate faster than expected. Ontario finds itself in supply shortfalls despite maintaining nuclear capacity, forcing reliance on natural gas peakers and imported power—undermining decarbonization goals.

5

Pickering Delay Leaves Ontario Short of Power and Paying More

Possible Resolves by End of 2031

Discussed by: The Globe and Mail, Ontario ratepayer advocates

Four Pickering reactors sit idle through the 2030s while Bruce Power's remaining units cycle through their own outages. If Pickering slips past its mid-2030s target, or Bruce hits trouble on Units 5, 7 or 8, Ontario covers the gap with gas-fired generation and imports, and the Globe reported concerns that this pushes power prices higher.

Historical Context

3 moments from history that rhyme with this story — and how they unfolded.

September 2008 - November 2012

Point Lepreau Refurbishment (2008-2012)

New Brunswick Power undertook Canada's first CANDU-6 refurbishment at the Point Lepreau Generating Station. The project was originally budgeted at $1.4 billion with an 18-month timeline. Technical challenges and scope changes pushed the final cost to approximately $2.4 billion, with the reactor returning to service three years late.

Then

New Brunswick faced electricity shortfalls and higher costs during the extended outage, importing power from neighboring provinces.

Now

The experience established lessons for subsequent CANDU refurbishments, influencing planning approaches at Bruce Power and OPG. The reactor has since operated reliably with an extended lifespan.

Why this matters now

Point Lepreau's difficulties contrast sharply with Bruce Power's on-time, on-budget performance, suggesting the industry has learned from early refurbishment challenges. The comparison is central to evaluating whether Bruce Power's success can continue through four more units.

April 2009 - July 2011

Wolsong Unit 1 Refurbishment (2009-2011)

Korea Hydro and Nuclear Power retubed the 679 MW Wolsong Unit 1 CANDU reactor in South Korea, marking the first successful CANDU-6 refurbishment completed on schedule. The project replaced all 380 fuel channels in 27 months, demonstrating that the technology could be refurbished efficiently.

Then

Wolsong-1 returned to service with a 25-year life extension, validating the economic case for CANDU refurbishment.

Now

The success influenced decisions to proceed with Canadian refurbishment programs. South Korea's expertise became a benchmark for the global CANDU operator community.

Why this matters now

Wolsong demonstrated that CANDU refurbishment could be executed efficiently when properly planned, providing a model that informed Bruce Power's approach. The 27-month timeline set expectations for what well-managed projects could achieve.

February 2016 - February 2026

Darlington Refurbishment (2016-2026)

Ontario Power Generation undertook refurbishment of all four Darlington reactors at a total cost of $12.8 billion, completing Unit 2 in 2020 and finishing the final Unit 4 in February 2026, ahead of schedule and $150 million under budget. The project was the largest infrastructure undertaking in Ontario's history.

Then

Darlington's 3,500 MW of capacity returns to full service, providing electricity for 3.5 million homes with a lifespan extended to at least 2055.

Now

The successful completion, announced just weeks before Bruce Power's Unit 3 milestone, demonstrates Ontario's nuclear industry can deliver complex megaprojects on time.

Why this matters now

Darlington's completion sets a benchmark for the remaining Bruce Power refurbishments. Both projects share contractors and workforce, meaning lessons transfer directly. The combined success strengthens the case for continued nuclear investment in Ontario.

Sources

(19)