Abu Dhabi's Taweelah C gas plant reaches financial close

Abu Dhabi's Taweelah C gas plant reaches financial close

Built World

TAQA, Aljomaih and Sembcorp lock in US$2.1 billion for 2.6 gigawatts of gas-fired capacity built to back up a fast-growing solar fleet

Overview

Updated 1 hour ago

Abu Dhabi closed US$2.1 billion of bank debt on 23 November for Taweelah C, a 2.6-gigawatt gas-fired power plant on the coast northeast of the city. Abu Dhabi National Energy Company (TAQA) holds 60% of the project; Saudi Arabia's Aljomaih Energy and Water and Singapore's Sembcorp Industries hold the rest.

The financing turns a June contract award into a project that can be built. Emirates Water and Electricity Company (EWEC), the state-backed buyer, has agreed to purchase every unit of electricity the plant produces through 2050.

Taweelah C is not a rival to solar. It exists to make solar usable at scale. EWEC plans to reach 15.5 gigawatts of photovoltaic capacity by 2030 and more than 35 gigawatts by 2035, and needs plants that can ramp quickly when the sun goes down.

China Energy Engineering Corporation holds the engineering, procurement and construction contract. Siemens Energy is supplying three gas turbines, two steam turbines and five generators. Commercial operation is targeted for 2029.

Why it matters

Abu Dhabi is adding gas capacity to keep AI data centres and cities powered while it scales solar, a model Gulf states are copying.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

2.6 GW
Planned generating capacity
A combined-cycle gas plant, sized to run as flexible back-up rather than baseload.
$2.1B
Debt raised at financial close
Long-term loans from a syndicate of regional and international banks, equivalent to 7.76 billion dirhams.
60%
TAQA's stake in the project company
The international consortium holds the other 40%; in the operations company the split flips to 60-40 in the consortium's favour.
15.5 GW
EWEC's solar target for 2030
Abu Dhabi's buyer plans more than 35 gigawatts of solar by 2035, which is the demand Taweelah C is meant to balance.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

TA
Abu Dhabi National Energy Company (TAQA)
State-linked energy company
Majority owner of the Taweelah C project company with a 60% stake

Abu Dhabi's main domestic energy company and the local partner in the emirate's independent power projects.

EW
Emirates Water and Electricity Company (EWEC)
State-backed power and water procurer
Sole purchaser of Taweelah C's electricity under a contract running to 2050

The Abu Dhabi body that buys, dispatches and sells power and water, and runs the tenders for new plants.

AE
Aljomaih Energy and Water Company
Saudi power and water developer
Part of the 40% international consortium in the project company

A Saudi developer that invests in power and water projects and co-leads the international side of Taweelah C.

SI
Sembcorp Industries
Singapore-listed energy and urban development company
Part of the 40% international consortium in the project company

A Singapore company that builds and operates power and water assets, including a large portfolio in the Gulf.

China Energy Engineering Group (中国能建)
China Energy Engineering Group (中国能建)
State-owned engineering and construction company
Holds the engineering, procurement and construction contract

The Beijing-based contractor responsible for building the plant, from civil works to commissioning.

Siemens Energy
Siemens Energy
Converter station contractor
Supplying the plant's turbines and generators

The German equipment maker supplying three gas turbines, two steam turbines and five generators.

TA
Taweelah C lender group
Bank syndicate
Provided the long-term debt for the plant

Local and international banks that arranged and funded the US$2.1 billion package.

Timeline

June 2026 November 2026

3 events Latest: Today
  1. Financial close on US$2.1 billion of debt

    Today Finance

    The partners close 7.76 billion dirhams in long-term financing with a syndicate of regional and international banks. Early works are under way.

  2. EWEC awards Taweelah C to TAQA-led group

    Award

    EWEC names TAQA, Aljomaih Energy and Water and Sembcorp Industries as partners and signs a power purchase agreement running to the end of 2050.

  3. Siemens Energy picked for turbine package

    Procurement

    Siemens Energy is selected to supply three gas turbines, two steam turbines, five generators and auxiliary systems.

Scenarios

1

Taweelah C enters commercial operation in 2029

Likely Resolves by End of 2029

Discussed by: TAQA, EWEC and the project partners, in the financial-close announcements

The schedule survived the financing stage. Early works have started at Al Taweelah and China Energy Engineering Corporation holds the construction contract, with Siemens Energy supplying the turbines. Hitting 2029 depends on equipment deliveries and on connecting the plant to the grid.

2

Developers commit to carbon capture at Taweelah C

Possible Resolves by End of 2028

Discussed by: EWEC and TAQA, which describe the plant as designed to allow carbon capture in future

The plant is being built capture-ready, meaning space and design provisions exist but no capture equipment is contracted and no operator has been named. A decision would most likely follow a carbon-capture project elsewhere in the emirate reaching commercial scale, or a buyer willing to pay a premium for lower-carbon power.

3

Construction slips and first power moves past 2029

Possible Resolves by End of 2029

Discussed by: No party has predicted a delay; the scenario rests on the gap between a financing milestone and an unbuilt plant

Financial close is not construction. The project still needs turbine deliveries from Siemens Energy, civil works at an operating coastal complex, and grid connections. Combined-cycle plants of this size routinely slip a year or more when equipment or commissioning runs late.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

October 2021 – December 2023

UAE net-zero pledge and COP28 (2021-2023)

The UAE became the first Gulf oil producer to commit to net-zero emissions by 2050, then hosted the COP28 climate summit in Dubai. That summit closed with an agreement, the UAE Consensus, calling on countries to transition away from fossil fuels in energy systems.

Then

Gulf producers argued that gas is a transition fuel and that continued hydrocarbon investment is compatible with their climate targets.

Now

Abu Dhabi's state companies kept adding gas-fired capacity, framing it as back-up for intermittent renewables rather than as baseload.

Why this matters now

Taweelah C is that argument in hardware: new fossil generation justified by the need to balance a grid filling up with solar.

2020 – 2024

Barakah nuclear plant (2020-2024)

The UAE connected the first of four reactors at Barakah, the Arab world's first nuclear plant, adding about 5.6 gigawatts of firm, carbon-free capacity to a grid that had relied almost entirely on gas.

Then

Nuclear took over a large share of baseload generation, cutting the gas burned around the clock.

Now

The plant gave the UAE dispatchable low-carbon power, but reactors cannot ramp up and down quickly, which left a need for flexible plants.

Why this matters now

Taweelah C fills the other half of the same problem: fast-ramping capacity to complement both nuclear baseload and solar peaks.

Sources