Eni and KazMunayGas commission gas plant in Kazakhstan's first hybrid power complex

Eni and KazMunayGas commission gas plant in Kazakhstan's first hybrid power complex

Built World

The 120MW Zhanaozen plant joins a 50MW solar farm to power oil and gas operations; a 77MW wind farm is due in 2027.

Overview

Updated 20 minutes ago

A 120-megawatt gas power plant has entered service in Zhanaozen, in western Kazakhstan's Mangystau Region. It is the second piece of a 247-megawatt complex that Eni and the national oil company KazMunayGas are building to keep oil and gas facilities powered.

The complex pairs a 50-megawatt solar farm, running since September 2025, with gas engines that can ramp up when sunlight fades. A 77-megawatt wind farm is under construction. The design is meant to give industrial customers steady power while drawing a substantial share from renewables.

Why it matters

If it works, the plant gives Kazakhstan's oil heartland reliable power with a large renewable share — a test case for other petrostates.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

247 MW
Planned hybrid capacity
Combined solar, gas and wind capacity when all three phases are complete.
120 MW
Gas plant capacity
Six Wärtsilä engines now fully commissioned in Zhanaozen.
35%
Expected renewable share
KazMunayGas's estimate of renewables' share of the complex's output once the wind farm is running.
26M kWh
Gas plant output since July 2026
Electricity generated from first industrial power to full commissioning.
93M kWh
Solar output since September 2025
Generation from the 50MW solar farm, per regional figures cited in November 2026.
$348M
Reported project investment
Figure from Construction Review; KazMunayGas's project page earlier listed US$322.5 million.
3M
Man-hours without a lost-time injury
Recorded during construction and commissioning of the gas plant.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

June 2023 November 2026

5 events Latest: Yesterday
Tap a bar to jump to that date
  1. 120MW gas plant fully commissioned

    Latest Commissioning

    Eni and KazMunayGas completed the gas phase after 12 months of construction and three million man-hours without a lost-time injury.

  2. Gas plant produces first industrial electricity

    Milestone

    The 120MW facility started feeding power ahead of full commissioning.

  3. 50MW solar farm enters service

    Commissioning

    The first phase of the hybrid complex began generating, later producing about 93 million kWh.

  4. Partners agree terms for renewable power sales and gas plant lease

    Negotiation

    KMG, Eni and industrial customers settled the principal terms for selling solar and wind power and leasing the gas plant.

  5. KMG and Eni sign principles agreement for Zhanaozen hybrid plant

    Agreement

    The deal was sealed at a meeting attended by Kazakhstan's head of state, setting up the 247MW project.

Scenarios

1

Wind farm enters service in 2027, completing the hybrid complex

Likely Resolves by End of 2027

Discussed by: Eni and KazMunayGas project updates

Eni says the wind farm's main civil works should finish by the end of 2026, letting turbine installation begin. Commercial operation is targeted for 2027. Hitting that target gives the complex all three power sources and the roughly 35% renewable share KMG expects.

2

Wind construction slips past 2027

Possible Resolves by End of 2027

Discussed by: Project schedule, phased buildout

The wind phase is the least advanced of the three. If civil works or turbine delivery slip, commercial operation moves past 2027 and the complex runs on solar and gas alone for longer.

3

KMG copies the solar-gas-wind model at another field

Uncertain Resolves by End of 2028

Discussed by: KMG project documents

KMG calls the hybrid design unique for Kazakhstan. If the Zhanaozen plant performs as planned, the company could copy the model at other fields facing power constraints.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

2023

Mangystau power constraints and oil-output risk (2023)

KazMunayGas designed the hybrid plant to cut the risk of oil production losses from emergency restrictions and outages at the Mangystau power unit. Planned customers included the Ozenmunaigas fields, slated to draw 91 megawatts, and the Kazakh Gas Processing Plant.

Then

KMG and Eni signed a principles agreement in June 2023 and settled power-sale and lease terms that October.

Now

The solar farm came online in September 2025; the gas plant followed in November 2026.

Why this matters now

The plant's purpose is reliability for oil and gas operations, which explains why gas sits at the center of a project marketed as renewable.

2020s

Kazakhstan's 2060 carbon-neutrality target (2020s)

Kazakhstan has set a goal of reaching carbon neutrality by 2060. Officials point to projects like the Mangystau complex as steps toward a lower-carbon power mix while the country keeps producing oil and gas.

Then

Backers cite the plant as a contribution to the goal.

Now

Whether the target changes the country's heavy reliance on fossil fuels is unresolved.

Why this matters now

The 2060 goal is the policy backdrop the project's backers invoke when describing the renewable share of its output.