Lake Turkana Wind Power, Kenya (2018)
A private consortium built roughly 310 megawatts of wind capacity in northern Kenya, backed by development lenders and selling to the state utility. The turbines were finished before the transmission line built to carry their power.
The plant waited on the grid, and the delay became a dispute over who covered the cost of the idle capacity.
The project became a reference point for African private-power deals: the offtake contract mattered as much as the construction contract.
Amunet II carries the same structure, a private owner selling to a state utility under a long-term contract, so the grid connection is the schedule risk that matters.