Pull to refresh
Logo
Egypt signs Amunet II wind contracts and moves to build its first turbine factory

Egypt signs Amunet II wind contracts and moves to build its first turbine factory

Built World

AMEA Power starts construction on a 500 MW farm at Ras Shukeir and, with Ming Yang, plans a turbine plant in the Suez Canal zone

Overview

Updated 58 minutes ago

Construction began in November 2026 on a 500-megawatt wind farm at Ras Shukeir, on Egypt's Red Sea coast. AMEA Power signed a $650 million engineering, procurement and construction contract with PowerChina Huadong Engineering on November 18 and expects the plant to run commercially by September 2028.

The site will hold 45 Ming Yang turbines of 11 megawatts each, spread over 54 square kilometers. The same signing covered a $200 million factory in the Suez Canal Economic Zone that would build those turbines in Egypt, with a first phase due to operate in the second half of 2028. AMEA Power owns the wind farm and sells the power to the Egyptian Electricity Transmission Company under a long-term contract, with debt from the International Finance Corporation.

Why it matters

Egypt is adding wind at gigawatt scale and, for the first time, plans to manufacture the turbines on its own soil.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

$650M
Amunet II investment
Total project cost for the 500 MW wind farm at Ras Shukeir.
500 MW
Installed capacity
Forty-five 11 MW turbines across 54 square kilometers.
45
Turbines
Ming Yang 11 MW machines, supplied through PowerChina Huadong.
2.3 billion kWh
Expected annual generation
PowerChina's estimate, enough for more than 500,000 households.
1.3M
Cost per megawatt
Project cost divided by capacity, at 500 MW.
3 GW
Planned factory output per year
Annual turbine capacity targeted at the Suez Canal Economic Zone plant.
$200M
Turbine factory investment
AMEA Power and Ming Yang's planned plant, built in two phases.
Sept 2028
Targeted commercial operation
AMEA Power's stated commissioning date, after a November 2026 construction start.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

June 2025 November 2026

6 events Latest: Today
Tap a bar to jump to that date
  1. Construction start and 2028 commissioning date confirmed

    Today Schedule

    AMEA Power's timeline puts construction in progress and commercial operation in September 2028.

  2. AMEA Power signs Amunet II construction contracts

    Contract

    PowerChina Huadong takes the $650 million EPC job; Ming Yang supplies 45 turbines of 11 MW.

  3. Egypt's first turbine factory deal signed

    Industry

    AMEA Power and Ming Yang agree a $200 million, 3 GW-a-year plant in the Suez Canal Economic Zone.

  4. Sany signs MoU for a turbine plant in the canal zone

    Industry

    A 2 GW-a-year plant, announced before AMEA Power and Ming Yang's larger 3 GW project.

  5. Egypt and AMEA Power agree Amunet 2 framework

    Agreement

    The Electricity Ministry's framework covered the 500 MW wind farm plus 300 MWh of battery storage.

  6. Amunet I comes online at Ras Ghareb

    Infrastructure

    AMEA Power's first Egyptian wind farm, 500 MW, was described at the time as the largest in Africa.

Scenarios

1

Amunet II reaches commercial operation by September 2028

Likely Resolves by End of 2028

Discussed by: AMEA Power's own project schedule, set out in its November 20, 2026 announcement

The EPC contract covers engineering through commissioning, handover and warranty, so PowerChina carries most of the construction risk. PowerChina has built three prior wind farms in Egypt, and the project has development-bank debt attached. Turbine deliveries through 2027 and a working grid connection at Ras Shukeir are the triggers to watch.

2

Amunet II slips past 2028 on grid or financing delays

Possible Resolves by Q2 2029

Discussed by: No party has publicly forecast a delay; the risk sits in the project's dependence on IFC debt and a new grid connection at Ras Shukeir

Egyptian wind projects have previously finished construction before the transmission link was ready, and a lender's conditions can hold up the first drawdown. If either slips, the September 2028 date moves. The clearest early signal would be a revised commissioning date in AMEA Power or PowerChina disclosures.

3

Suez Canal turbine factory starts production in 2028

Possible Resolves by Q2 2029

Discussed by: Hussain Al Nowais, who gave the two-phase timeline at the signing

Al Nowais said phase one would operate in the second half of 2028 and phase two by the end of 2029, reaching 3 GW a year. A Chinese partner supplying the machinery and a state zone offering the land make the schedule plausible. What is not yet shown is whether Egyptian-assembled turbines can win orders beyond AMEA Power's own pipeline.

Historical Context

3 moments from history that rhyme with this story — and how they unfolded.

2014-2018

Lake Turkana Wind Power, Kenya (2018)

A private consortium built roughly 310 megawatts of wind capacity in northern Kenya, backed by development lenders and selling to the state utility. The turbines were finished before the transmission line built to carry their power.

Then

The plant waited on the grid, and the delay became a dispute over who covered the cost of the idle capacity.

Now

The project became a reference point for African private-power deals: the offtake contract mattered as much as the construction contract.

Why this matters now

Amunet II carries the same structure, a private owner selling to a state utility under a long-term contract, so the grid connection is the schedule risk that matters.

2018-2019

Benban Solar Park, Egypt (2018-2019)

Egypt assembled more than 30 privately owned solar plants of about 1.65 gigawatts total near Aswan, financed largely by development banks and selling power to the state under long-term contracts.

Then

The complex became one of the largest solar installations in the world and drew the lending relationships Egypt later reused.

Now

It established the template AMEA Power now uses on wind: private ownership, state offtake, development-bank debt.

Why this matters now

Amunet II is that same model applied to wind, at roughly a third of Benban's capacity in a single contract.

June 2025

Ras Ghareb wind expansion (2025)

AMEA Power commissioned the 500 MW Amunet wind farm at Ras Ghareb, described at the time as the largest wind farm in Africa.

Then

It doubled as a proving ground for AMEA Power's Egyptian supply chain and construction partners.

Now

Amunet II takes the same developer and the same EPC model to a second Red Sea site, pushing AMEA Power's Egyptian wind capacity to 1 GW.

Why this matters now

The first plant is the reason the second one could be financed and contracted quickly.

Sources

(5)