Hainan closes its 500 kV ring, lifting island power transfer more than fourfold

Hainan closes its 500 kV ring, lifting island power transfer more than fourfold

Built World

A 5.7 billion yuan loop of 838 km replaces the island's 220 kV backbone and ties 14 cities into one grid

Overview

Updated 7 minutes ago

For two decades Hainan's power moved on a 220 kV backbone, an island grid joined to the mainland by two cables and cut off by every big storm. On Dec. 15, 2025, China Southern Power Grid closed a 500 kV loop around the whole island: 838 km of line, three new substations, 14 cities connected.

The loop is the difference between a grid that can accept power and one that cannot. Planned offshore wind farms, the second phase of the Changjiang nuclear plant and rooftop solar all need a wire that reaches the whole island. Eleven months on, peak demand has set five records, hitting 9.02 GW, up 10.4%.

Why it matters

Hainan's grid was sized for a quiet island. It now has to carry offshore wind, nuclear power and the load of China's customs-free trade hub.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

838 km
New 500 kV transmission line
Longer than one full circuit of the island coastline.
4x+
Island power transfer capacity
The grid's transmission capacity rose more than fourfold; one 500 kV circuit carries four to five times a 220 kV line.
¥5.7B
Project investment
Funded by China Southern Power Grid; part of a 46 billion yuan Hainan plan for 2026-2030.
3,750 MVA
New substation capacity
Three 500 kV substations and five main transformers added at Yecheng, Changhua and Sanya.
87.1%
Clean energy share of installed capacity
As of November 2025, among the highest shares of any Chinese province.
73.03%
Clean energy share of generation
The ring was built to raise this share by absorbing more wind and solar.
9.02 GW
Peak electricity demand, 2026
Set after five record highs in one year; up 10.4% on the prior peak.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

September 2024 2026

5 events Latest: 2026
Tap a bar to jump to that date
  1. Southern Grid lifts Hainan investment to 46 billion yuan

    Latest Investment

    Plan covers 2026-2030, up 68%; 2026 spending alone forecast at 11 billion.

  2. Peak demand breaks five records

    Demand

    Load reaches 9.02 GW, 10.4% above the previous high.

  3. Buried feeders reach 96 coastal towns

    Resilience

    86% of the 'one town, one cable' target completed in high-wind areas.

  4. 500 kV ring enters service

    Infrastructure

    838 km loop, three substations, 14 cities, more than 4x transfer capacity.

  5. Typhoon Yagi wrecks Hainan's distribution grid

    Disaster

    More than 41,000 workers repair 14,000 km of lines over roughly 20 days.

Scenarios

1

Hainan's peak load crosses 10 GW with no curtailment

Likely Resolves by Oct 31, 2027

Discussed by: Hainan Power Grid planners and Southern Grid load forecasters

Peak demand hit 9.02 GW in 2026 and the utility forecasts 15.5 GW by 2030, with electricity use growing about 10% a year. A hot summer in 2027 is the first real test of whether the ring and the 45 new 220 kV projects absorb that growth, or whether the island falls back on ordering factories to stop.

2

Clean sources pass 80% of Hainan's generation

Possible Resolves by End of 2028

Discussed by: Hainan Power Grid planning staff and provincial energy officials

Clean plants supplied 87.1% of installed capacity and 73.03% of generation in November 2025. The ring was sized to carry offshore wind from 11 planned farms totaling 12.3 GW off Lingao, Danzhou and Dongfang. If those connect on the current schedule, the generation share crosses 80%.

3

The 500 kV ring rides out a typhoon without losing a line

Uncertain Resolves by End of 2028

Discussed by: Southern Grid engineers and provincial emergency planners

Towers, conductors and fittings were built to a 100-year return-period wind standard, and the ring gives the island two paths to each load center. The design claim gets tested the first time a strong typhoon crosses the island: does the 500 kV loop stay energized while lower-voltage lines fail?

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

July 2014

Typhoon Rammasun (2014)

Rammasun crossed Hainan as a super typhoon, bringing down transmission towers and cutting power across large parts of the island. Reinforcement crews were shipped in from the mainland to rebuild overhead lines.

Then

Overhead lines were rebuilt within weeks and power restored neighborhood by neighborhood.

Now

The storm became the reference point for Hainan's wind standards; the new ring is built to a 100-year return period.

Why this matters now

It set the pattern the 500 kV loop is meant to break: one storm, one island, days of outage.

September 2024

Typhoon Yagi (2024)

Yagi hit Hainan as a super typhoon and wrecked the distribution network around Haikou and Wenchang. Southern Grid moved more than 41,000 workers across the strait and repaired over 14,000 km of medium- and low-voltage lines in about 20 days.

Then

Most of the damaged distribution network was rebuilt within a month.

Now

The response exposed how much of Hainan's grid was still overhead and radial, a weakness the buried-cable program targets.

Why this matters now

The 500 kV ring and the 'one town, one cable' program are the two direct answers to Yagi.