Taishan Phase I: the first EPRs to run (2009-2019)
Taishan units 1 and 2 were built with the European Pressurised Reactor designed in France, with construction starting in 2009 and 2010. Both units ran about five years behind their original 2013-2014 target. Unit 1 nonetheless became the first EPR anywhere to enter commercial operation, in December 2018, with unit 2 following in September 2019.
The delays made Taishan a reference case for first-of-a-kind reactor cost and schedule risk.
CGN kept the site and its workforce but switched designs for the next phase, choosing the domestically developed Hualong One instead of more EPRs.
Phase II is being built at the same site by the same company but with a different reactor family, so Taishan now tests whether a repeated domestic design moves faster than an imported first-of-a-kind one.