Gazprom commissions first unit at South Yakutian power plant

Gazprom commissions first unit at South Yakutian power plant

Built World

A 110 MW gas turbine enters service at Chulman, the first piece of a 313 MW station meant to power the Eastern Polygon railways and southern Yakutia's coal mines

Overview

Updated Yesterday

The first 110-megawatt turbine at the South Yakutian Thermal Power Plant entered service on November 25, 2026. Construction at Chulman, in Yakutia's Neryungri district, began in June 2024.

Two more units are planned: a second 110-megawatt gas turbine and a 93-megawatt steam turbine, which together would bring the station to 313 megawatts. Its output is aimed first at the Eastern Polygon rail network that carries Russian freight toward Asian ports, and at the coal mines of southern Yakutia. Fuel arrives through an 8-kilometre branch off the Power of Siberia pipeline.

Why it matters

Yakutia's mines and eastbound rail traffic have outgrown the region's power supply; this plant is the first new generation to close the gap.

Questions about this story

Free account needed to ask — your question is kept and asked for you right after sign-up. Answers are public.

No questions yet — be the first to ask.

Key Indicators

110 MW
Capacity of the first unit
The gas turbine commissioned on November 25, 2026.
313 MW
Planned station capacity
Two gas turbines plus one steam turbine, once all three units run.
93 MW
Steam turbine capacity
The third unit, scheduled for 2027, which turns the plant into a combined-cycle facility.
8 km
Gas branch line length
Spur connecting the plant to the Power of Siberia pipeline.
2,000 MW
Generation under construction in Yakutia
Figure cited by head of the republic Aisen Nikolaev for all energy projects now building in Yakutia.

Voices

Curated perspectives — historical figures and your fellow readers.

Sign up to generate historical perspectives on this story.

People Involved

Organizations Involved

Timeline

June 2024 November 2026

5 events Latest: Yesterday
Tap a bar to jump to that date
  1. First 110 MW unit in service

    Latest Commissioning

    Gazprom brought the plant's first gas turbine online at a ceremony with the energy minister, Miller and Nikolaev; the unit entered service on November 25.

  2. Gazprom signals two-stage launch

    Statement

    First phase is near completion, with commissioning slated for October 2026 and October 2027.

  3. Turbine installation reported on track

    Construction

    Natsproektstroy confirms progress on turbine installation and plant systems.

  4. Cabinet approves capital costs

    Regulatory

    The Russian government signs off on capital spending for the project.

  5. Ground broken at Chulman

    Construction

    Crews begin building the station in Yakutia's Neryungri district.

Scenarios

1

Second gas turbine adds 110 MW before the new year

Likely Resolves by End of 2026

Discussed by: Aisen Nikolaev, head of Yakutia, cited by the republic's news agency YSIA

Nikolaev said a second 110-megawatt unit is planned to start before the end of 2026, which would take the station to 220 megawatts and roughly double the new capacity available to the southern Yakutian grid. Fedorov has separately said the full station is a 2027 milestone, leaving room for the second turbine to arrive first.

2

Station reaches full 313 MW in 2027

Possible Resolves by Jan 31, 2028

Discussed by: Denis Fedorov, general director of Gazprom Energoholding

Fedorov said the company intends to complete construction next year and hit the 313-megawatt design capacity. Reaching it requires the 93-megawatt steam turbine, which converts the exhaust heat from both gas turbines into extra power and lifts fuel efficiency above that of simple-cycle operation.

3

Steam turbine slips past 2027, plant stays at 220 MW

Unlikely Resolves by Q2 2028

Discussed by: No named forecaster; the risk is implied by the project's staged schedule and its September 2026 slip from October

The first phase had been slated for October 2026 and landed in late November, a one-month movement. A repeat on the second phase would leave the plant at 220 megawatts, burning gas without the efficiency gain of combined-cycle operation and delivering fewer megawatts to the railway and the mines.

Historical Context

2 moments from history that rhyme with this story — and how they unfolded.

2014-2019

Power of Siberia pipeline launch (2019)

Russia built a gas pipeline from its eastern fields to the Chinese border and began deliveries in December 2019, opening an export route that had not existed before. The line runs through Yakutia, which had previously used its gas mainly for local needs.

Then

Gazprom gained a long-term export contract and a pipeline corridor across a sparsely served region.

Now

The pipeline made gas-fired power possible at sites far from the western grid, including Chulman.

Why this matters now

The plant burns gas delivered through an 8-kilometre branch off that pipeline, so its fuel supply and its economics sit downstream of an export project.

1974-1984

Baikal-Amur Mainline construction (1974-1984)

The Soviet state mobilised a national construction effort to lay a second rail route to the Pacific, north of the existing Trans-Siberian line. The route was completed in 1984 but moved far less freight than planned for decades afterward.

Then

A rail corridor opened through permafrost and mountains at enormous cost.

Now

The line became the backbone of today's Eastern Polygon, whose capacity Russia is now spending to expand.

Why this matters now

The Eastern Polygon's expansion is the direct successor to that project, and electricity, not track, is now the constraint on how much freight it can carry.