UK commits £196 million to HALEU enrichment (May 2024)
The UK government awarded Urenco £196 million under a program committing up to £300 million to build a domestic HALEU supply chain. Capenhurst became a roughly £400 million project including Urenco's own contribution.
Gave Urenco a funded path to a commercial enrichment plant with a 2031 target.
Created the only Western facility that advanced reactor developers could contract with for HALEU in the early 2030s.
Blykalla's contract exists because that plant is being built. Its delivery date depends on it.